Bridgestone Retail Operations LLC..<br />

Invitation to Bid<br />

cannot be repaired and therefore you will be required to remove and replace the<br />

damaged area of the slab from saw cut joint to saw cut joint.<br />

i. Fixture Equipment deliveries of Bridgestone Retail Operations LLC supplied material is<br />

on a tight schedule and will be ONLY be phased according to the following schedule and<br />

will be released from a consolidated warehouse by the Bridgestone Retail Operations<br />

LLC Zone Construction Manager ONLY. NOTE that the purpose of the #2.5 delivery<br />

of shelving is to allow the installation early enough to permit the installation of fire<br />

sprinkler and lighting prior to inspections for turnover is applicable. The building<br />

however must be completely secure at that time which is estimated to be<br />

approximately 32 days prior to turnover.<br />

July 5, 2012 Updated New Store Invitation to Bid Revised 07-05-2012 Page 12