11-D-801, TA-55 Reinvestment Project – Phase II (TRP II)<br />

Los Alamos National Laboratory (LANL), Los Alamos, New Mexico<br />

Project Data Sheet (PDS) is for Construction<br />

1. Significant Changes<br />

<strong>The</strong> most recent DOE O 413.3B approved Critical Decision (CD) is CD-1, Approve Alternative<br />

Selection and Cost Range for all three phases <strong>of</strong> TRP II that was approved on July 15, 2008 with a<br />

preliminary cost range <strong>of</strong> $75,400 to $99,900 and a preliminary CD-4 date <strong>of</strong> <strong>FY</strong> 2016.<br />

Phase A: Glovebox #1 and Air Dryers<br />

<strong>The</strong> most recent DOE O 413.3B approved CD is CD-2 for Phase A, Approve Performance Baseline that<br />

was approved on November 24, 2009 with a Total Project Cost (TPC) <strong>of</strong> $19,470 and a CD-4 date <strong>of</strong><br />

May 2013.<br />

Phase B: Glovebox #2, Confinement Doors, and Demolition <strong>of</strong> Plutonium Facility (PF)-7 in<br />

support <strong>of</strong> the Uninterruptible Power Supply (UPS)<br />

<strong>The</strong> most recent DOE O 413.3B approved CD is CD-2 for Phase B, Approve Performance Baseline that<br />

was approved on June 3, 2010 with a TPC <strong>of</strong> $18,203 and a CD-4 date <strong>of</strong> February 2014.<br />

Phase C: Glovebox #3, Exhaust Stack, UPS, Criticality Alarm System, and Vault Water Tanks<br />

<strong>The</strong> most recent DOE O 413.3B approved CD is CD-1, Approve Alternative Selection and Cost Range<br />

that was approved on July 15, 2008 with a TPC not to exceed $66,227. A performance baseline (CD-2)<br />

is anticipated by the 3Q <strong>FY</strong> 2011.<br />

This phased critical decision approach and schedule is consistent with the tailoring strategy that has been<br />

approved by the NNSA Acquisition Executive.<br />

As stated in the <strong>FY</strong> 2010 President’s Budget Request, (06-D-140 data sheet), “construction and final<br />

design funding for TRP II will be requested in the future via a new PDS.” This data sheet meets that<br />

commitment and includes the TRP II final design scope and funding.<br />

A Federal Project Director at the appropriate level has been assigned to this project.<br />

This PDS is an update to the <strong>FY</strong> 2011 PDS. Project progress is noted in Section 2 below.<br />

Weapons Activities/RTBF/Construction/<br />

11-D-801, TA-55 Reinvestment Project II, LANL Page 175<br />