3. Baseline and Validation Status<br />

TEC, TEC,<br />

(dollars in thousands)<br />

OPC<br />

Prelim Final TEC, TEC, Except OPC,<br />

Design Design Construction Total D&D D&D OPC, Total TPC<br />

<strong>FY</strong> 2011 13,684 TBD TBD TBD TBD N/A TBD TBD<br />

<strong>FY</strong> <strong>2012</strong> 14,684 12,700 56,715 84,099 1 5,477 N/A 15,477 99,576<br />

Phase A: Glovebox #1 and Air Dryers<br />

TEC, TEC,<br />

(dollars in thousands)<br />

OPC<br />

Prelim Final TEC, TEC, Except OPC,<br />

Design Design Construction Total D&D D&D OPC, Total TPC<br />

<strong>FY</strong> 2011 3,700 TBD 15,330 19,030 440 N/A 440 19,470<br />

<strong>FY</strong> <strong>2012</strong> 4,289 1,848 12,448 18,585 443 N/A 443 19,028<br />

Phase B: Glovebox 2, Confinement Doors, and Demo <strong>of</strong> PF-7 in support <strong>of</strong> the UPS<br />

(dollars in thousands)<br />

TEC, TEC,<br />

OPC<br />

Prelim Final TEC, TEC, Except OPC,<br />

Design Design Construction Total D&D D&D OPC, Total TPC<br />

<strong>FY</strong> <strong>2012</strong> 5,069 854 11,041 16,964 621 N/A 621 17,585<br />

Phase C: Glovebox 3, Exhaust Stack, UPS, Criticality Alarm System, and Vault Water Tanks<br />

(dollars in thousands)<br />

TEC,<br />

OPC<br />

Prelim Final TEC, TEC, Except OPC,<br />

Design Design Construction Total D&D D&D OPC, Total TPC<br />

<strong>FY</strong> <strong>2012</strong> 5,326 9,998 33,226 4 3,224 14,413 N/A 14,413 6 2,963<br />

4. Project Description, Justification, and Scope<br />

<strong>The</strong> LANL PF-4 major facility and infrastructure systems are aging and approaching the end <strong>of</strong> their<br />

service life, and, as a consequence, are beginning to require excessive maintenance. As a result, the<br />

facility is experiencing increased operating costs and reduced system reliability. Compliance with safety<br />

and regulatory requirements is critical to mission essential operations, and thus becoming more costly<br />

and cumbersome to maintain due to the physical conditions <strong>of</strong> facility support systems and equipment.<br />

This project will enhance safety and enable cost effective operations so that the facility can continue to<br />

support critical Defense Programs missions and activities. <strong>The</strong> LANL identified 20 subprojects at the<br />

pre-conceptual stage for upgrades and modernization. <strong>The</strong> subprojects were selected utilizing a riskbased<br />

prioritization process that considered the current condition <strong>of</strong> the equipment, risk <strong>of</strong> failure to the<br />

worker, the environment, and the public, and risk <strong>of</strong> failure to programmatic and facility operations.<br />

During Conceptual Design, the project continued to refine the prioritization method and subprojects.<br />

Defense Program’s Infrastructure Revitalization combined with impacts to available/anticipated funding<br />

has led to development <strong>of</strong> a phased acquisition strategy for the TRP project. To meet mission need<br />

objectives within the budgetary and strategic context constraints, the TRP project is proposed for<br />

execution as three separate, distinct capital line item projects, TRP Phase I, TRP Phase II, and TRP<br />

Phase III.<br />

Weapons Activities/RTBF/Construction/<br />

11-D-801, TA-55 Reinvestment Project II, LANL Page 177<br />

<strong>FY</strong> <strong>2012</strong> <strong>Congressional</strong> Budget