02.08.2013 Views

Department of Energy FY 2012 Congressional ... - The FIRE Place

Department of Energy FY 2012 Congressional ... - The FIRE Place

Department of Energy FY 2012 Congressional ... - The FIRE Place

SHOW MORE
SHOW LESS

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

operations and from other selected inventories <strong>of</strong> weapon-grade plutonium within the Enterprise. <strong>The</strong><br />

facility will have the capacity to store sufficient plutonium oxide for two years <strong>of</strong> operations.<br />

<strong>The</strong> MOX facility will be approximately 441,000 square feet in size and provide all <strong>of</strong> the material<br />

processing and fabrication operations needed to produce MOX fuel. <strong>The</strong> MOX facility operations<br />

include: aqueous polishing (AP) to purify the plutonium oxide; blending and milling; pelletizing;<br />

sintering; grinding; loading fuel rods; bundling fuel assemblies; and storing feed material, pellets, and<br />

fuel assemblies. <strong>The</strong> facility also includes a laboratory and space for material sampling and use by a<br />

monitoring and inspection team. Adjacent to the MOX process areas is the secure shipping and<br />

receiving area to support material receipt, utilities, and technical support.<br />

<strong>The</strong> design <strong>of</strong> the MOX Fuel Fabrication Facility (MFFF) is based on technologies, processes, and<br />

facilities that have been successfully operating in France for decades, specifically AREVA’s MELOX<br />

and La Hague facilities. <strong>The</strong> facility will meet U.S. conventions, codes, standards, and regulatory<br />

requirements, and will be licensed by the Nuclear Regulatory Commission (NRC).<br />

<strong>The</strong> MFFF has the following key performance parameters: (1) fabricate 3.5 MT <strong>of</strong> weapon-grade<br />

plutonium annually into mixed-oxide fuel qualified for use in U.S. commercial nuclear power plants;<br />

and (2) provide the capability to successfully process alternate (non-pit) feedstock.<br />

<strong>FY</strong> 2010 Current Project Status:<br />

Project activities continue to focus on the completion <strong>of</strong> engineering, civil/structural construction, the<br />

procurement and receipt <strong>of</strong> long-lead equipment, along with the assembly and testing <strong>of</strong> process units.<br />

Through August 2010, the project has installed over 76,000 cubic yards <strong>of</strong> reinforced concrete and more<br />

than 15,000 tons <strong>of</strong> rebar in the MFFF. Initial testing was completed on the first gloveboxes and process<br />

equipment, and piping/heating ventilation and air conditioning (HVAC) installation began this year.<br />

Tank installation and coatings are continuing. Permanent underground utility installation continued,<br />

including domestic water, electrical, fire protection, and sanitary sewer, along with installation <strong>of</strong> the<br />

radioactive liquid waste transfer lines. <strong>The</strong> project also completed construction <strong>of</strong> two more buildings; a<br />

Secured Warehouse and a new Electrical Substation. Eleven auxiliary buildings are now complete. <strong>The</strong><br />

project completed this work while achieving over four million safe work hours.<br />

<strong>FY</strong> 2011 and <strong>FY</strong> <strong>2012</strong> Description <strong>of</strong> Activities<br />

In <strong>FY</strong> 2011, construction will continue with the third floor slab and walls being completed in Aqueous<br />

Polishing (AP) and the second floor slab being completed in the MOX processing area. Trapped<br />

equipment will continue to be installed as the main processing facility construction progresses. Process<br />

piping installation will continue as will the design and construction <strong>of</strong> the Technical Support Building.<br />

Electrical conduit and raceway installation will begin along with initiation <strong>of</strong> the fire protection system<br />

installation. <strong>The</strong> HVAC will continue and construction <strong>of</strong> the Reagent Building and the Emergency<br />

Diesel Generator Building will begin.<br />

In <strong>FY</strong> <strong>2012</strong>, the MFFF structural construction package will be completed, including completion <strong>of</strong> the<br />

primary exterior wall and MFFF ro<strong>of</strong>. HVAC, Reagent Building, Emergency Diesel Generator<br />

Building, and Technical Support Building construction will continue. Process piping installation will<br />

continue as will glovebox installation/connections and electrical installation.<br />

Defense Nuclear Nonproliferation/<br />

Fissile Materials Disposition/<br />

99-D-143, Mixed Oxide (MOX)<br />

Fuel Fabrication Facility Page 394<br />

<strong>FY</strong> <strong>2012</strong> <strong>Congressional</strong> Budget

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!