Explanation <strong>of</strong> Funding Changes<br />

U.S. Surplus Fissile Materials Disposition<br />

U.S. Plutonium Disposition: <strong>The</strong> overall decrease results from a<br />

combination <strong>of</strong> decreasing PDC OPC since the majority <strong>of</strong> the<br />

workscope will be funded from TEC until the project is baselined,<br />

decreased MIFT funding reflecting the decision to proceed with a dry<br />

versus wet process for depleted uranium conversion, and delays in<br />

implementing reactor modifications for MOX fuel use.<br />

<strong>FY</strong> <strong>2012</strong> vs.<br />

<strong>FY</strong> 2011<br />

Request<br />

($000)<br />

-4,150<br />

U.S. Uranium Disposition: <strong>The</strong> increase supports the contractor<br />

projected escalation rates applied to the down-blending <strong>of</strong> surplus<br />

HEU for disposition. +450<br />

Total, U.S. Fissile Materials Disposition O&M -3,700<br />

U.S. Fissile Materials Disposition Construction<br />

99-D-141-02 Waste Solidification Building (WSB): <strong>The</strong><br />

decrease reflects the completion <strong>of</strong> initial large outlays needed by<br />

the Balance <strong>of</strong> Plant sub-contractor and a decline in long-lead<br />

procurements, as well as completion <strong>of</strong> physical construction. -39,418<br />

99-D-141-01 Pit Disassembly and Conversion (PDC): <strong>The</strong><br />

increase supports PDC critical design work scope and<br />

documentation supporting stabilization and packaging (S&P) and<br />

material storage (MS) Critical Decisions in <strong>FY</strong> <strong>2012</strong> and the<br />

initiation <strong>of</strong> long-lead procurement to support the early MOX<br />

feed portion <strong>of</strong> the project. +96,000<br />

99-D-143 Mixed Oxide (MOX) Fuel Fabrication Facility:<br />

<strong>The</strong> decrease reflects the completion <strong>of</strong> long-lead equipment<br />

procurements and facility design activities. -90,616<br />

Total, U.S. Fissile Materials Disposition Construction -34,034<br />

Defense Nuclear Nonproliferation/<br />

Fissile Materials Disposition Page 386<br />

<strong>FY</strong> <strong>2012</strong> <strong>Congressional</strong> Budget