Total Estimated Cost (TEC)<br />

5. Financial Schedule<br />

(dollars in thousands)<br />

App ropriations Obligations Costs<br />

PED<br />

<strong>FY</strong> 2010 6,655 a<br />

6,655 2, 666<br />

<strong>FY</strong> 2011 0 0 3,989<br />

Total, PED 6,655 6,655 6,655<br />

Construction<br />

<strong>FY</strong> 2010 5,845 5,845 0<br />

<strong>FY</strong> 2011 0 5,845<br />

<strong>FY</strong> <strong>2012</strong> 35,387 35,387 8 ,206<br />

<strong>FY</strong> 2013 17,909 17,909 2 6,578<br />

<strong>FY</strong> 2014 0 0 12,665<br />

<strong>FY</strong> 2015 0 0 5,847<br />

Total, Construction 59,141 59,141 59,141<br />

TEC<br />

<strong>FY</strong> 2010 12,500 12,500 2,666<br />

<strong>FY</strong> 2011 0 0 9,834<br />

<strong>FY</strong> <strong>2012</strong> 35,387 35,387 8,206<br />

<strong>FY</strong> 2013 17,909 17,909 26,578<br />

<strong>FY</strong> 2014 0 0 12,665<br />

<strong>FY</strong> 2015 0 0 5,847<br />

Total, TEC 65,796 65,796 65,796<br />

Other Project Cost (OPC)<br />

OPC except D&D<br />

<strong>FY</strong> 2009 2855 2855 2855<br />

<strong>FY</strong> 2010 264 264 264<br />

<strong>FY</strong> 2011 1,501 1,501 1,501<br />

<strong>FY</strong> <strong>2012</strong> 803 803 80 3<br />

<strong>FY</strong> 2013 661 661 66 1<br />

<strong>FY</strong> 2014 1,714 1,714 1, 714<br />

<strong>FY</strong> 2015 1,224 1,224 1,224<br />

<strong>FY</strong> 2016 978 978 978<br />

Total, OPC except D&D 10,000 10,000 10,000<br />

D&D NA NA NA<br />

<strong>FY</strong> 2010 NA NA NA<br />

Total, D&D NA NA NA<br />

a $12,500 was originally requested as PED funding in the <strong>FY</strong> 2010 project data sheet. $5,845 <strong>of</strong> uncosted balances from<br />

PED will be used to procure long-lead items. <strong>The</strong> DOE Order 413.3B allows placement <strong>of</strong> long-lead equipment before the<br />

overall start <strong>of</strong> construction is approved.<br />

Weapons Activities/RTBF/Construction/<br />

10-D-501, Nuclear Facility Risk Reduction, Y-12 Page 188<br />

<strong>FY</strong> <strong>2012</strong> <strong>Congressional</strong> Budget