(dollars in thousands)<br />

App ropriations Obligations Costs<br />

Total Project Cost (TPC)<br />

<strong>FY</strong> 2004 1,552 1,552 1,552<br />

<strong>FY</strong> 2005 3,565 3,565 1,984<br />

<strong>FY</strong> 2006 4,552 4,552 3,661<br />

<strong>FY</strong> 2007 3,038 3,038 2,921<br />

<strong>FY</strong> 2008 227 227 2,056<br />

<strong>FY</strong> 2009 3,327 3,327 1,295<br />

<strong>FY</strong> 2010 3,448 3,448 3,006<br />

<strong>FY</strong> 2011 725 725 3,959<br />

<strong>FY</strong> <strong>2012</strong> 25,508 25,508 22,244<br />

<strong>FY</strong> 2013 11,867 11,867 9,941<br />

<strong>FY</strong> 2014 0 0 5,190<br />

Total, TPC 57,809 57,809 57,809<br />

6. Details <strong>of</strong> Project Cost Estimate<br />

(dollars in thousands)<br />

Current Previous Original<br />

Total Total Validated<br />

Estimate Estimate Baseline<br />

Total Estimated Cost (TEC)<br />

Design (PED)<br />

Design 6 ,407 5,853 5,853<br />

Contingency 47 6 1,030 1,030<br />

Total, PED (PED no. 04D-140) 6,883 6,883 6,883<br />

Construction<br />

Site Preparation 9,778 7,688 7,688<br />

Equipment 3, 103 3,976 3,976<br />

Other Construction 24,923 22,978 22,978<br />

Contingency 5, 000 3,058 3,058<br />

Total, Construction 42,804 37,700 37,700<br />

Total, TEC 49,687 44,583 44,583<br />

Contingency, TEC 5,476 4,088 4,088<br />

Other Project Cost (OPC)<br />

OPC except D&D<br />

Conceptual Planning a<br />

Conceptual Design 262 262 262<br />

Start-Up 6, 996 6,859 6,859<br />

Contingency 40 2 379 379<br />

Total, OPC except D&D 7,660 7,500 7,500<br />

a <strong>The</strong> cost for the conceptual design was included in the Phase 1. <strong>The</strong> project was split in two phases after CD-0 approval.<br />

Weapons Activities/RTBF/Construction<br />

09-D-404, Test Capabilities Revitalization-Phase II, SNL Page 198<br />

<strong>FY</strong> <strong>2012</strong> <strong>Congressional</strong> Budget