02.08.2013 Views

Department of Energy FY 2012 Congressional ... - The FIRE Place

Department of Energy FY 2012 Congressional ... - The FIRE Place

Department of Energy FY 2012 Congressional ... - The FIRE Place

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

TEC, TEC,<br />

(dollars in thousands)<br />

OPC OPC,<br />

PED Construction TEC, Total Except D&D D&D OPC, Total TPC<br />

<strong>FY</strong> 2008 31,183 171,013 202,196 42,908 N/A 42,908 245,104<br />

<strong>FY</strong> 2009 36,102 159,367 195,469 82,718 N/A 82,718 278,187<br />

<strong>FY</strong> 2010 42,542 201,789 244,331 100,124 N/A 100,124 344,455<br />

<strong>FY</strong> 2011 42,652 201,679 244,331 100,124 N/A 100,124 344,455<br />

<strong>FY</strong> <strong>2012</strong> 42,652 201,679 244,331 100,124 N/A 100,124 344,455<br />

4. Project Description, Justification, and Scope<br />

Waste Solidification Building (WSB):<br />

<strong>The</strong> WSB will process radioactive liquid waste streams from the Mixed Oxide Fuel Fabrication Facility<br />

(MFFF) and pit disassembly and conversion operations into a solid form for ultimate disposal. <strong>The</strong><br />

MFFF will produce approximately 85 percent <strong>of</strong> the waste that the WSB will process. <strong>The</strong> WSB must<br />

be operational to support mixed oxide (MOX) cold start-up testing activities scheduled in the<br />

2013 timeframe. <strong>The</strong> radioactive liquid waste consists <strong>of</strong> one high-activity and two low-activity<br />

streams. <strong>The</strong> high-activity stream contains significant amounts <strong>of</strong> americium removed from plutonium<br />

oxide during MOX aqueous polishing operations. <strong>The</strong> low-activity streams contain stripped uranium<br />

also removed from MOX aqueous polishing operations and laboratory waste from pit disassembly and<br />

conversion operations. <strong>The</strong> WSB operating life is expected to be approximately 15 years; however the<br />

facility has a design life <strong>of</strong> 30 years and could easily be extended to accommodate disposition <strong>of</strong><br />

additional surplus plutonium. After completing its mission, the WSB will be deactivated,<br />

decontaminated, and decommissioned over three to four years.<br />

<strong>The</strong> scope <strong>of</strong> this project consists <strong>of</strong> the following activities: design, construction, procurement,<br />

installation, testing, demonstration, and start-up testing <strong>of</strong> structures and equipment. <strong>The</strong> processing<br />

facility will be approximately 33,000 square feet and is designed as a single story structure <strong>of</strong> hardened<br />

concrete. An additional separate structure consisting <strong>of</strong> a covered concrete pad will be constructed to<br />

provide temporary storage <strong>of</strong> containerized waste following treatment prior to packaging for shipment.<br />

<strong>The</strong> major process equipment includes tanks, evaporators, and solidification equipment.<br />

<strong>The</strong> WSB has the following key performance parameters: (1) demonstrate the ability to process the<br />

anticipated waste volumes <strong>of</strong> the high activity waste stream and the two low activity waste streams, and<br />

(2) demonstrate the ability to produce waste products that are within the established limits <strong>of</strong> the Waste<br />

Acceptance Criteria and/or Documented Safety Analysis <strong>of</strong> the receiving facilities.<br />

<strong>FY</strong> 2010 Project Status:<br />

Project activities continue to focus on the civil/structural construction and the procurement and receipt<br />

<strong>of</strong> long lead equipment. <strong>The</strong> early site construction sub-contract has completed all site preparation and<br />

installation <strong>of</strong> underground utilities (service water, fire mains, process sewer, sanitary sewer, and<br />

electrical feeds). <strong>The</strong> structural basemat has been completed and work continues on the facility wall<br />

construction. Reinforcing steel, the floor drain tank, the electrical substation, gloveboxes, safety-related<br />

ventilation fans, and HEPA filter housings have been received as part <strong>of</strong> the long-lead procurement<br />

activities. Fabrication is continuing on the process tanks, evaporators, and cementation units, with<br />

delivery anticipated in 4Q <strong>FY</strong> 2010 or 1Q <strong>FY</strong> 2011.<br />

Defense Nuclear Nonproliferation/<br />

Fissile Materials Disposition/<br />

99-D-141-02, Waste Solidification Building Page 403<br />

<strong>FY</strong> <strong>2012</strong> <strong>Congressional</strong> Budget

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!