08-D-802, High Explosive Pressing Facility<br />

Pantex Plant, Amarillo, Texas<br />

Project Data Sheet (PDS) is for Construction<br />

1. Significant Changes<br />

<strong>The</strong> most recent DOE O 413.3B approved Critical Decision (CD) is CD-3, Approve Start <strong>of</strong><br />

Construction that was approved on May 15, 2008 with a Total Project Cost (TPC) <strong>of</strong> $80,578 and CD-4<br />

in the second quarter <strong>of</strong> <strong>FY</strong> 2011.<br />

Latest approved Baseline Change was on January 9, 2009, with a TPC <strong>of</strong> $116,038 and CD-4 <strong>of</strong> May<br />

2014. <strong>The</strong> project was placed on hold during <strong>FY</strong> 2009 at the completion <strong>of</strong> design activities. In<br />

<strong>FY</strong> 2011, construction is planned to commence. This project must be rebaselined to support the<br />

<strong>FY</strong> <strong>2012</strong> – <strong>FY</strong> 2016 budget process as a result <strong>of</strong> the hold and the reduction <strong>of</strong> all existing uncosted<br />

project balances in <strong>FY</strong> 2010. A Baseline Change Proposal (BCP) will be prepared; as part <strong>of</strong> the BCP<br />

development, a cost estimate and external independent review will be performed to ensure the project is<br />

ready to begin construction, as well as update the project’s cost and schedule. Upon approval <strong>of</strong> the<br />

BCP, a revised TPC and CD-4 date will be established. <strong>The</strong> current un-validated estimate is<br />

approximately $146 million with a CD-4 in the first quarter <strong>of</strong> <strong>FY</strong> 2017. Construction funding being<br />

requested under this data sheet is less than the baseline TEC. A request for proposals has been issued<br />

and a construction contract should be awarded in the spring <strong>of</strong> 2011. Based on the actual contract, the<br />

baseline will be recalculated.<br />

A Federal Project Director at the appropriate level has been assigned to this project.<br />

This PDS is an update <strong>of</strong> the <strong>FY</strong> 2011 PDS and reflects progress to date.<br />

2. Design, Construction, and D&D Schedule<br />

(fiscal quarter or date)<br />

CD-0 CD-1<br />

PED<br />

Complete CD-2 CD-3 CD-4 D&D Start<br />

D&D<br />

Complete<br />

<strong>FY</strong> 2008 8/8/2003 7/19/2005 3Q<strong>FY</strong>2007 11/21/2006 4Q<strong>FY</strong>2008 2Q<strong>FY</strong>2011 N/A N/A<br />

<strong>FY</strong> 2009 8/8/2003 7/19/2005 4Q<strong>FY</strong>2008 11/21/2006 4Q<strong>FY</strong>2008 3Q<strong>FY</strong>2014 N/A N/A<br />

<strong>FY</strong> 2011 8/8/2003 7/19/2005 3 Q<strong>FY</strong>2009 11/21/2006 5/15/2008 1 Q<strong>FY</strong>2017 N/A N/A<br />

<strong>FY</strong> <strong>2012</strong> 8/8/2003 7/19/2005 3 Q<strong>FY</strong>2009 11/21/2006 5/15/2008 1 Q<strong>FY</strong>2017 N/A N/A<br />

CD-0 – Approve Mission Need<br />

CD-1 – Approve Alternative Selection and Cost Range<br />

CD-2 – Approve Performance Baseline<br />

CD-3 – Approve Start <strong>of</strong> Construction<br />

CD-4 – Approve Start <strong>of</strong> Operations or Project Closeout<br />

D&D Start – Start <strong>of</strong> Demolition & Decontamination (D&D) work<br />

D&D Complete – Completion <strong>of</strong> D&D work<br />

Weapons Activities/RTBF/Construction/<br />

08-D-802, HE Pressing Facility, PX Page 201<br />

<strong>FY</strong> <strong>2012</strong> <strong>Congressional</strong> Budget