MECON LIMITED<br />

REGD. OFF : RANCHI (BIHAR)<br />

PROCESS & PIPING<br />

DESIGN SECTION<br />

NEW DELHI<br />

\\Akjha\work contrac\standard TS for Pipe Line WC (Vol-<strong>II</strong>) MASTER FOLDER\04A major water crossing\Major Water Crossing -Final 04.doc<br />

STANDARD SPECIFICATION<br />

TITLE MAJOR WATER CROSSINGS SPECIFICATION NO. PAGE 4 OF 14<br />

c) Buoyancy studies<br />

MEC/S/05/62/04 REVISION 0<br />

d) Preparation <strong>of</strong> fabrication yard and launching areas.<br />

e) Pipeline construction details (handling, stringing, welding, concrete<br />

coating etc.)<br />

f) Pre-test procedure including trial mix, design & tests for concrete coating.<br />

g) Procedure for corrosion coating <strong>of</strong> field joint<br />

h) Dredging, anchoring program, spoil-deposit and trench survey method<br />

including facilities for COMPANY.<br />

i) Pulling or other installation method and related calculations.<br />

j) Pulling arrangement including launchway and anchoring and breaking<br />

device.<br />

k) Trench correction before launching.<br />

l) Method <strong>of</strong> positioning and sinking <strong>of</strong> pipeline.<br />

m) Method <strong>of</strong> rectification <strong>of</strong> damages to the pipeline, during launching.<br />

n) Method <strong>of</strong> backfilling, bank protection and survey.<br />

o) Final test procedure after backfilling.<br />

p) Safety systems during launching, rope tests.<br />

q) Communication.<br />

r) Abandonment and recovery procedures concurred.<br />

s) Necessary permission from concerned authorities for crossing.<br />

COMPANY shall inform CONTRACTOR within 21 days if any objection against<br />

the document and procedure described requires resubmission by<br />

CONTRACTOR.<br />

Approval by COMPANY <strong>of</strong> the methods used by CONTRACTOR shall in no way<br />

relieve CONTRACTOR from the sole responsibility for safe and satisfactory<br />

installation <strong>of</strong> the crossing.