MECON LIMITED<br />

REGD. OFF : RANCHI (BIHAR)<br />

PROCESS & PIPING<br />

DESIGN SECTION<br />

NEW DELHI<br />

STANDARD SPECIFICATION<br />

TITLE WELDING OF ONSHORE GAS<br />

SPECIFICATION NO. PAGE 17 OF 48<br />

PIPELINES<br />

MEC/S/05/62/02 REVISION<br />

Any weld which as a result <strong>of</strong> radiographic and/ or ultrasonic examination in the<br />

opinion <strong>of</strong> COMPANY exhibits imperfections greater than the limits stated in API-<br />

1104 latest edition or as superseded in this article shall be considered defective<br />

and shall so be marked with an identification paint marker.<br />

In addition to the API-1104 requirements, the welds containing cracks including<br />

crater cracks regardless <strong>of</strong> size <strong>of</strong> location is unacceptable.<br />

1. Any length <strong>of</strong> inadequate penetration <strong>of</strong> the root bead as defined by API-<br />

1104 is not acceptable except that root concavity is allowed as per API<br />

1104.<br />

2. Any amount <strong>of</strong> incomplete fusion at the root <strong>of</strong> the joint as detailed in API<br />

1104 is considered unacceptable.<br />

3. Unrepaired burn through areas are unacceptable.<br />

Suitable records shall be maintained by the CONTRACTOR as desired by the<br />

COMPANY on the day to day work done on welding, radiography, ultrasonic<br />

testing. The CONTRACTOR shall present the records to the COMPANY on day<br />

to day basis and whenever demanded, for approval.<br />

12.6 Destructive Testing<br />

The COMPANY has the authority to order the cutting <strong>of</strong> upto 0.1% <strong>of</strong> the total<br />

number <strong>of</strong> welds completed for destructive testing at no extra cost <strong>of</strong> COMPANY.<br />

The destructive testing <strong>of</strong> weld joints shall be made as per Clause 14.0.<br />

In addition, welds already cut out for defects for any reason may also be<br />

subjected to destructive testing. The sampling and the re-execution <strong>of</strong> welds shall<br />

be carried out by the CONTRACTOR at his own expense. If the results are<br />

unsatisfactory, welding operations shall be suspended and may not be restarted<br />

until the causes have been identified and the CONTRACTOR has adopted<br />

measures which guarantee acceptable results. If it is necessary in the<br />

COMPANY's opinion the procedure shall be re-qualified. The weld joint<br />

represented by unsatisfactory welds shall stand rejected unless investigation<br />

prove otherwise.<br />

13.0 REPAIR OF WELDS<br />

13.1 With the prior permission <strong>of</strong> COMPANY, welds which do not comply with the<br />

standards <strong>of</strong> acceptability shall be repaired or the joint cut out and re-welded.<br />

\\Akjha\work contrac\standard TS for Pipe Line WC (Vol-<strong>II</strong>) MASTER FOLDER\02A welding onshore gas pipeline\Welding <strong>of</strong> Onshore Gas Pipelines with addendum - I 02A.doc