MECON LIMITED<br />

REGD. OFF : RANCHI (BIHAR)<br />

Document6<br />

PROCESS & PIPING<br />

DESIGN SECTION<br />

NEW DELHI<br />

TITLE MAINLINE CONSTRUCTION<br />

(ONSHORE)<br />

STANDARD SPECIFICATION<br />

SPECIFICATION NO. PAGE 33 OF 53<br />

MEC/S/05/62/01 REVISION A<br />

9.1.6 Wherever the pipeline is laid under tension, as a result <strong>of</strong> an assembly error (for<br />

example, incorrect positioning <strong>of</strong> bends, either horizontal or vertical), the trench<br />

shall be rectified or in exceptional cases a new assembly shall be carried out, to<br />

be approved by COMPANY, so that it fits the excavation and the laying bed.<br />

9.1.7 Laying shall be carried out under safe conditions so as to avoid stresses and<br />

temporary deformations <strong>of</strong> the equipments which may cause damage to the<br />

pipeline itself and to the coating. In localised points where the right-<strong>of</strong>-way is<br />

restricted to the minimum necessary for the transit <strong>of</strong> mechanical equipment, the<br />

laying shall be carried out using other suitable means. The pipe shall be placed<br />

on the floor or the excavation, without jerking, falling, impact or other similar<br />

stresses. In particular, care must be taken that the deformation caused during<br />

the raising <strong>of</strong> the pipe work from the supports, does not exceed the values for<br />

the minimum allowable radius <strong>of</strong> elastic curvature, so as to keep the stresses on<br />

the steel and on the coating within safe limits. The portion <strong>of</strong> the pipeline<br />

between trench and bank shall be supported by as many side-booms as<br />

required and approved by COMPANY for holding the line in gentle S-curve<br />

maintaining minimum elastic bend radius as specified in job standard. Lowering<br />

in and back-filling shall preferably be carried out at the highest ambient<br />

temperature.<br />

9.1.8 The pipeline must be laid without interruption for the whole or the length <strong>of</strong><br />

section available. Where water is present, no laying shall be permitted until the<br />

ditch has been drained to the extent and for the time necessary to make visual<br />

inspection possible <strong>of</strong> the bed on which the pipe is to be laid. Following such<br />

inspections, the presence <strong>of</strong> water will be permitted, provided that it is not so<br />

high as to cause cave-in <strong>of</strong> the walls <strong>of</strong> the trench or floating <strong>of</strong> the pipeline<br />

before backfilling, when weighting is not provided for the pipe.<br />

9.1.9 CONTRACTOR shall take precautions immediately after lowering in to prevent<br />

the movement <strong>of</strong> the pipe in trench.<br />

9.1.10 In laying parallel pipelines in the same trench, the minimum distances between<br />

the pipeline indicated in the approved drawings shall be observed. Once the first<br />

pipeline has been positioned, it shall in no way be disturbed by laying <strong>of</strong> the<br />

subsequent pipeline.