MECON LIMITED<br />

REGD. OFF : RANCHI (BIHAR)<br />

PROCESS & PIPING<br />

DESIGN SECTION<br />

NEW DELHI<br />

STANDARD SPECIFICATION<br />

TITLE QUALITY ASSURANCE SYSTEMS SPECIFICATION NO. PAGE 3 OF 9<br />

REQUIREMENTS MEC/S/05/62/66 REVISION 0<br />

Special Process<br />

Processes requiring pre-qualification <strong>of</strong> their process capability.<br />

3.0 CONTRACTORS SCOPE OF WORK<br />

3.1 Prior to award <strong>of</strong> contract<br />

The bidder shall understand scope <strong>of</strong> work, drawings, specifications and<br />

standards etc., attached to the tender/ enquiry document, before he makes an<br />

<strong>of</strong>fer.<br />

The bidder shall submit milestone chart showing the time required for each<br />

milestone activity and linkages between different milestone activities alongwith<br />

overall time period required to complete the entire scope <strong>of</strong> work.<br />

The bidder shall develop and submit manpower and resource deployment<br />

chart.<br />

The bidder shall submit, alongwith the bid, a manual or equivalent document<br />

describing/ indicating/ addressing various control/ check points for the purpose<br />

<strong>of</strong> quality assurance and the responsibilities <strong>of</strong> various functions responsible<br />

for quality assurance.<br />

3.2 After the award <strong>of</strong> contract<br />

The bidder shall submit the schedule for submission <strong>of</strong> following documents in<br />

the kick-<strong>of</strong>f meeting or within two weeks <strong>of</strong> the placement <strong>of</strong> order, whichever<br />

is earlier.<br />

• Detailed Bar Chart<br />

• Quality plan for all activities, required to be done by the bidder, to<br />

accomplish <strong>of</strong>fered scope <strong>of</strong> work.<br />

• Inspection and test plans, covering various control aspects.<br />

• Job procedures as required by MECON/ Owner.<br />

• Procurement schedule for items to be supplied by contractor covering<br />

inspection <strong>of</strong> the same.<br />

Various documents submitted by the bidder shall be finalised in consultation<br />

with MECON. Here it shall be presumed that ones a bidder has made an <strong>of</strong>fer,<br />

he has understood the requirements given in this specification and agrees to<br />

\\Akjha\work contrac\standard TS for Pipe Line WC (Vol-<strong>II</strong>) MASTER FOLDER\66 quality assurance system\Specification - Quality Assurance Plan - Reqd. - 66.doc