MECON LIMITED<br />

REGD. OFF: RANCHI (BIHAR)<br />

PROCESS & PIPING<br />

DESIGN SECTION<br />

NEW DELHI<br />

TITLE PIPING FABRICATION AND<br />

ERECTION<br />

STANDARD SPECIFICATION<br />

SPECIFICATION NO. PAGE 5 OF 62<br />

MEC/S/05/62/06 REVISION 0<br />

5.1.2 There can be some variations in the dimensions and level appearing in the<br />

arrangement drawings and those actually occurring at site due to minor<br />

variations in the location <strong>of</strong> equipments, structures, cut out etc. Adequate field<br />

joints shall be provided, permitting assembly and erection <strong>of</strong> pipe work without<br />

major modification.<br />

5.2 Supporting<br />

Location and design <strong>of</strong> pipe supports shown in approved drawings and support<br />

drawings shall be strictly followed.<br />

5.2.1 Supports shall be installed in such a way that they do not contribute to over<br />

stressing <strong>of</strong> a line.<br />

5.2.2 Fabrication and erection <strong>of</strong> additional supporting elements and structural fixtures<br />

which in COMPANY's view are required for proper supporting <strong>of</strong> the system,<br />

shall be carried out by CONTRACTOR at no extra cost.<br />

5.2.3 All temporary supports, elements required for alignment, erection and assembly<br />

shall be removed after completion <strong>of</strong> work.<br />

5.3 Equipment hook-up<br />

5.3.1 Prior to hook-up, the alignment and trueness <strong>of</strong> flange faces shall be checked to<br />

ensure that no undue stresses shall be induced in the system while hooking up.<br />

6.0 INSPECTION<br />

6.1<br />

6.2 CONTRACTOR shall provide all facilities/ assistance to COMPANY for proper<br />

execution <strong>of</strong> their inspection without any extra charge.<br />

6.3 All piping work shall be subjected to inspection by COMPANY at any time during<br />

fabrication. CONTRACTOR shall furnish to COMPANY detailed work<br />

programme sufficiently in advance, in order to enable COMPANY to arrange for<br />

inspection.