MECON LIMITED<br />

Delhi<br />

PROCESS & PIPING<br />

DESIGN SECTION<br />

TECHNICAL SPECIFICATION FOR<br />

TEMPORARY CATHODIC<br />

PROTECTION SYSTEM<br />

TECHNICAL SPECIFICATION NO. : MEC/TS/05/62/016A REV-1 Page 9 <strong>of</strong> 19<br />

6.3 Test Stations<br />

Recommended dimensional tolerance shall be as follows:<br />

Length ± 2.5%<br />

Width/thickness ± 5%<br />

6.3.1 Test stations shall be provided along the pipeline ROW for monitoring the performance<br />

<strong>of</strong> the Cathodic Protection system at intervals not exceeding 1000 meters in<br />

uncongested & 250 meters in congested area unless otherwise specified. In addition<br />

to above, test stations shall also be provided at the following locations:<br />

a. At both sides <strong>of</strong> major road crossings<br />

b. At all insulating joints<br />

c. At vulnerable locations with drastic changes in soil resistivity<br />

d. At connections <strong>of</strong> surge diverters, grounding cells and polarisation cells<br />

e. At HT AC/DC overhead line crossings and selected locations where HT<br />

overhead line is in the vicinity <strong>of</strong> the pipeline.<br />

f. At railway line crossings and running parallel to the pipeline.<br />

g. At both sides <strong>of</strong> major river crossings.<br />

h. At high voltage cable crossings or along routes where HV cables are running in<br />

parallel.<br />

i. In the vicinity <strong>of</strong> DC net works or grounding system where interference<br />

problems are suspected.<br />

j. At crossings/parallel running <strong>of</strong> other pipeline structures<br />

k. At both sides <strong>of</strong> cased crossings<br />

l. At any other locations considered vulnerable locations where interference is<br />

expected<br />

m. At any other locations considered necessary by owner/owner’s representative<br />

6.3.2 Test stations for bonding shall be provided with shunt and resistor as a means to<br />

monitor and control current.<br />

6.3.3 Test stations used for sacrificial anodes shall have shunt for measurement <strong>of</strong> anode<br />

current, and provision for resistance insertion to limit the anode current output.<br />

6.3.4 Test station with current measuring facility shall be provided at each intermediate CP<br />

station drainage point (to measure pipeline from drainage point), at interference prone<br />

areas, on both sides <strong>of</strong> major river crossings and at least at two additional locations<br />

along the pipeline ROW between two CP stations.<br />

6.3.5 All test stations shall have weather pro<strong>of</strong> enclosure, having degree <strong>of</strong> protection IP 55<br />

with hinged lockable shutter. Enclosure shall be made <strong>of</strong> sheet steel <strong>of</strong> at least 3 mm<br />

thickness and shall be suitable for M.S. post mounting. The test stations shall be<br />

D:\old data\FATEH\MP Region\Kailaras\Tender RFQ\TCP&PCP\Temporary Cathodic Protection - 016A-R1.doc