MECON LIMITED<br />

REGD. OFF : RANCHI (BIHAR)<br />

Document6<br />

PROCESS & PIPING<br />

DESIGN SECTION<br />

NEW DELHI<br />

TITLE MAINLINE CONSTRUCTION<br />

(ONSHORE)<br />

STANDARD SPECIFICATION<br />

SPECIFICATION NO. PAGE 50 OF 53<br />

MEC/S/05/62/01 REVISION A<br />

14.14 In crop fields the tillage shall consist <strong>of</strong> passing over the land several times with<br />

a disc harrow, cultivating with a spading machine, or plow, to a depth <strong>of</strong> approx.<br />

20 cm. In general the ROW has also to be ripped. After this cultivation process<br />

no closed-in layers must be found in the ROW. The equipment used and<br />

methods adopted shall require the approval <strong>of</strong> COMPANY. Ripping, has to be<br />

done with rippers with a distance <strong>of</strong> 50 cm between the ripper blades. The type<br />

to be used shall be approved by COMPANY.<br />

14.15 A sapling <strong>of</strong> any plant/tree uprooted or cut during construction shall be planted<br />

along the route as per the direction <strong>of</strong> the COMPANY and in accordance with<br />

the Forest Preservation Act, 1981. The cost <strong>of</strong> sapling and its plantation shall be<br />

to CONTRACTOR's account.<br />

14.16 The ROW and the backfilled trench in particular has to be finished in such a way<br />

that after settlement <strong>of</strong> the soil the fields are at their original level.<br />

If during the maintenance period certain parts <strong>of</strong> the ROW are lower than the<br />

original level, COMPANY can order CONTRACTOR to bring these parts to the<br />

original level. If the level <strong>of</strong> the ROW for clean-up is ordered by COMPANY, risk<br />

<strong>of</strong> above mentioned additional restoration shall not be to CONTRACTOR's<br />

account.<br />

In cases where heavy damage has occurred to the structure <strong>of</strong> the subsoil as a<br />

result <strong>of</strong> special circumstances, COMPANY reserves the right to order<br />

CONTRACTOR to carry out special work. Said special work can include:<br />

- spading with dragline (depth 30 - 80 cm);<br />

- spading with dragline (depth 80 - 100 cm);<br />

- fertilizing;<br />

- cover with sand.<br />

If during clean-up operations, soil shortages become apparent outside the<br />

trench, CONTRACTOR shall supplement said soil shortage using suitable<br />

materials, approved by COMPANY.