MECON LIMITED<br />

Delhi<br />

PROCESS & PIPING<br />

DESIGN SECTION<br />

TECHNICAL SPECIFICATION<br />

FOR<br />

PIPELINE CROSSINGS USING<br />

HORIZONTAL DIRECTIONAL<br />

DRILLING METHOD<br />

TECHNICAL SPECIFICATION NO. : MEC/S/05/62/75 REV-0 Page 6 <strong>of</strong> 11<br />

2.9 Contractor shall, based on result <strong>of</strong> design and engineering carried out by him,<br />

prepare construction drawings for the crossing and shall submit the same for<br />

Owner’s approval. Construction drawings shall indicate the pipeline pr<strong>of</strong>ile with<br />

levels furnished at sufficient intervals for proper control during construction.<br />

Other relevant details viz., entry and exit angles, radius <strong>of</strong> bends, etc. shall<br />

also be indicated. Contractor shall also calculated the total length <strong>of</strong> pipeline<br />

required as well as the maximum tension required on the pull head <strong>of</strong> the rig.<br />

2.10 All construction works shall be carried out in accordance with the construction<br />

drawings approved by Owner.<br />

2.11 Before commencement <strong>of</strong> any field work, Contractor shall furnish for Owner’s<br />

approval all design calculations and construction drawings as stipulated in the<br />

above clauses.<br />

3.0 CONSTRUCTION<br />

Contractor shall comply with all the conditions and requirements issued by<br />

Authorities having jurisdiction in the area where the work is to be performed.<br />

If no public road exists, Contractor shall arrange on his own for access to his<br />

work area at no extra cost to owner.<br />

3.1.0 Installation Procedure<br />

3.1.1 Contractor shall, before commencing any work at site, submit for Owner’s<br />

approval a detailed installation procedure.<br />

3.1.2 The installation procedure as a minimum shall include the following:<br />

a) Project Organisation Chart:<br />

This shall indicate Contractor’s organisational set-up at site and<br />

manpower deployment.<br />

b) Details <strong>of</strong> fabrication yard and launching areas.<br />

c) Details <strong>of</strong> Equipment :<br />

Contractor shall furnish the complete list <strong>of</strong> all equipment to be<br />

deployed for preparation <strong>of</strong> pipe string and installation <strong>of</strong> crossing.<br />

Technical characteristics and capacity <strong>of</strong> each equipment including<br />

instrumentation, monitoring and control equipment shall be furnished in<br />

details.<br />