TITLE MAINLINE CONSTRUCTION<br />

(ONSHORE)<br />

6.5 Cutting and Removal <strong>of</strong> Paving<br />

STANDARD SPECIFICATION<br />

SPECIFICATION NO. PAGE 23 OF 53<br />

MEC/S/05/62/01 REVISION A<br />

Whenever it is permitted by Authorities and / or COMPANY to open cut a paved<br />

road crossing, or where the line is routed within the road pavement,<br />

CONTRACTOR shall remove the paving in accordance with the restrictions and<br />

requirements <strong>of</strong> the authorities having jurisdiction there<strong>of</strong> or as directed by<br />

COMPANY. The open cut for the road crossing shall be carried out only when<br />

the section <strong>of</strong> pipeline to be laid is complete. After laying the pipeline, backfilling<br />

shall be immediately performed and all the area connected with the works shall<br />

be temporarily restored.<br />

Throughout the period <strong>of</strong> execution <strong>of</strong> such works, CONTRACTOR shall provide<br />

and use warning signs, traffic lights or lanterns, barricades, fencing, watchman,<br />

etc. as required by the local authorities having jurisdiction and/ or COMPANY.<br />

For all roads, paths, walkway etc. which are open-cut, CONTRACTOR shall<br />

provide temporary diversions properly constructed to allow the passage <strong>of</strong><br />

normal traffic with the minimum <strong>of</strong> inconvenience and interruptions.<br />

The paving shall be restored to its original condition after the pipeline is installed.<br />

6.6 Extra Depth and Clearance<br />

At points where the contour <strong>of</strong> the earth way require extra depth to fit the<br />

minimum radius <strong>of</strong> the bend as specified or to eliminate unnecessary bending <strong>of</strong><br />

the pipe according to customary good pipeline practice, or where a deep trench<br />

is required at the approaches to crossings <strong>of</strong> roadways, railroads, rivers,<br />

streams, drainage ditches, and the like, CONTRACTOR shall excavate such<br />

additional depth as may be necessary at no extra cost to the COMPANY.<br />

CONTRACTOR shall excavate to additional depth where the pipeline<br />

approaches and crosses other pipelines, sewers, drain pipes, water mains,<br />

telephone, conduits, and other underground structures, so that the pipeline may<br />

be laid with at least 50 centimeters free clearance from the obstacle or as<br />

specified in the drawings, or such greater minimum distances as may be<br />

required by authorities having jurisdiction.