MECON LIMITED<br />

Delhi<br />

PROCESS & PIPING<br />

DESIGN SECTION<br />

TECHNICAL SPECIFICATION<br />

FOR<br />

PIPELINE CROSSINGS USING<br />

HORIZONTAL DIRECTIONAL<br />

DRILLING METHOD<br />

TECHNICAL SPECIFICATION NO. : MEC/S/05/62/75 REV-0 Page 4 <strong>of</strong> 11<br />

2.5 Pipeline Axis<br />

The plane containing the pipeline route axis shall be perpendicular to the<br />

horizontal plane. There shall be no bending <strong>of</strong> the pipeline route axis at<br />

depths shall lower than 2 meters below ground level.<br />

2.6 Back-reamed hole and Pipeline Interface<br />

2.6.1 Contractor shall derive combination <strong>of</strong>:<br />

- Back-reamed hole diameter<br />

- Bentonite density<br />

- Pipeline submerged weight in bentonite (and means to achieve that<br />

weight)<br />

to optimise the crossing design in terms <strong>of</strong> pipeline stresses and power<br />

requirement<br />

2.6.2 Contractor shall indicated what maximum shear stress in the pipeline coating<br />

will result from his choice <strong>of</strong> above parameters and other characteristics<br />

described in this section.<br />

2.6.3 Contractor shall furnish all calculations for Onner’s approval. If shear stress in<br />

pipe coating is, in the opinion <strong>of</strong> Owner, beyond the permissible limits,<br />

Contractor shall revise his choice <strong>of</strong> parameters to reduce shear stress on pipe<br />

coating to permissible value.<br />

2.7 Contractor shall determine in the minimum allowable elastic bend radius for<br />

pipe from the following consideration:<br />

2.7.1 Maximum Longitudinal Stress During Installation<br />

Total maximum longitudinal stress in the pipeline due to tension and bending<br />

at any location shall not exceed 90% <strong>of</strong> the SMYS <strong>of</strong> the pipe material.<br />

Contractor shall, in order to check this requirement, evaluate the maximum<br />

tensile forces to which the pipeline is subjected to at any phase <strong>of</strong> its<br />

installation during the pulling operation.<br />

\\Akjha\work contrac\standard TS for Pipe Line WC (Vol-<strong>II</strong>) MASTER FOLDER\75 pipe line crossing using HDD method\Specification for PL CUHDDM 75.doc