MECON LIMITED<br />

REGD. OFF : RANCHI (BIHAR)<br />

Document6<br />

PROCESS & PIPING<br />

DESIGN SECTION<br />

NEW DELHI<br />

TITLE MAINLINE CONSTRUCTION<br />

(ONSHORE)<br />

STANDARD SPECIFICATION<br />

SPECIFICATION NO. PAGE 19 OF 53<br />

MEC/S/05/62/01 REVISION A<br />

Beside recording the stamped - in pipe numbers, length <strong>of</strong> pipe and painted-on<br />

serial numbers, the stamped-in numbers <strong>of</strong> T-pieces, bends, valves, etc. and the<br />

batch numbers <strong>of</strong> bends, T-pieces, valves, etc. and the make <strong>of</strong> valves, shall<br />

also be recorded in said list.<br />

Before a pipe length, pipe end, etc. is cut the painted serial number and<br />

stamped-in pipe number shall be transferred by CONTRACTOR in the presence<br />

<strong>of</strong> COMPANY to either side <strong>of</strong> the joint which is to be made by cutting, and the<br />

changes shall be recorded in the above mentioned list stating the (new) length.<br />

The results shall be such that all pipes, pups, etc. <strong>of</strong> diameter greater than 2"<br />

bear clear marks painted on.<br />

CONTRACTOR shall explicitly instruct his staff that parts which cannot be<br />

identified must not be removed, except after permission by COMPANY.<br />

As a general rule parts must be marked as described above before being<br />

moved. In no conditions may unmarked parts be incorporated into the WORK.<br />

6.0 TRENCHING<br />

6.1 Location<br />

6.2 Excavation<br />

CONTRACTOR shall, excavate and maintain the pipeline trench on the staked<br />

center line <strong>of</strong> the pipeline taking into account the curves <strong>of</strong> the pipeline.<br />

6.2.1 CONTRACTOR shall, by any method approved by COMPANY, dig the pipeline<br />

trench on the cleared and graded Right-<strong>of</strong>-Way. In cultivable land and other<br />

areas specifically designated by the COMPANY, top 60mm <strong>of</strong> the arable soil on<br />

the pipeline trench top and 500mm on either side shall be excavated and stored<br />

separately to be replaced in original position after backfilling and compacting<br />

rest <strong>of</strong> the trench.<br />

Suitable crossing shall be provided and maintained over the open ROW where<br />

necessary, to pemit general public, property owners or his tenants to cross or<br />

move stock or equipment from one side <strong>of</strong> the trench to the other.