Above 250 & upto 500 - Deploy one qualified and experienced<br />

safety Engineer/ Officer who will guide<br />

the workers from time to time as well as<br />

impart basic guideline & training at least<br />

weakly once.<br />

Above 500 - One additional safety engineer/Officer<br />

(for every 500 or less) whose function will be as mentioned<br />

above<br />

Contractor shall indemnify and hold harmless <strong>GAIL</strong>/ MECON & their<br />

representative’s from any and all liabilities arising out <strong>of</strong> non fulfillment <strong>of</strong><br />

HSE requirements.<br />

3.1.4 The Contractor shall ensure that the Health, Safety and Environment<br />

(HSE) requirements are clearly understood & faithfully implemented at all<br />

levels, at each and every site/ work place.<br />

3.1.5 The Contractor shall promote and develop consciousness for Healthy,<br />

Safety and Environment among all personnel working for the Contractor.<br />

Regular awareness programs and fabrication shop/work site meeting shall<br />

be arranged on HSE activities to cover hazards involved in various<br />

operations during construction.<br />

3.1.6 Arrange suitable first aid measures such as First Aid Box, trained<br />

personnel to give First Aid, Stand by Ambulance or Vehicle and install fire<br />

protection measures such as: adequate number <strong>of</strong> steel buckets with sand<br />

and water and adequate fire extinguishers to the satisfaction <strong>of</strong> <strong>GAIL</strong>/<br />

MECON.<br />

3.1.7 The Contractor shall evolve a comprehensive planned and documented<br />

system for implementation and monitoring <strong>of</strong> the HSE requirements. This<br />

shall submitted to <strong>GAIL</strong> & MECON for approval well in advance, prior to<br />

start <strong>of</strong> work. The monitoring for implementation shall be done by regular<br />

inspection and compliance to the observations there<strong>of</strong>. The Contractor<br />

shall get similar HSE requirements implemented at his sub-contractor (s)<br />

work site/ Office. However, compliance <strong>of</strong> HSE requirement shall be the<br />

sole responsibility <strong>of</strong> the Contractor. Any review/ approval by <strong>GAIL</strong>/<br />

MECON shall not absolve the Contractor <strong>of</strong> his responsibility/ liability in<br />

relation to all HSE requirements.<br />

3.1.8 Non-Conformance on HSE by the Contractor (including his Subcontractors)<br />

as brought out during review/ audit by MECON/ OWNER<br />

representative shall be resolved forthwith by Contractor. Compliance<br />

report shall be possibility submitted to MECON/ <strong>GAIL</strong> at the earliest.<br />

Page 2 <strong>of</strong> 19