MECON LIMITED<br />

REGD. OFF : RANCHI (BIHAR)<br />

Document6<br />

PROCESS & PIPING<br />

DESIGN SECTION<br />

NEW DELHI<br />

TITLE MAINLINE CONSTRUCTION<br />

(ONSHORE)<br />

STANDARD SPECIFICATION<br />

SPECIFICATION NO. PAGE 46 OF 53<br />

MEC/S/05/62/01 REVISION A<br />

12.4.4 The in-line inserting shall be made on the buried pipeline; care shall be taken to<br />

operate at an external temperature as close as possible to the pipeline operating<br />

temperature.<br />

The joints shall be inserted on straight sections and laid on a fine sand bed.<br />

12.4.5 During the execution <strong>of</strong> the in-line connection welding, the propagation <strong>of</strong> heat<br />

shall be avoided. To achieve this, the joint shall be kept cold by means <strong>of</strong> nags<br />

continuously wetted.<br />

12.4.6 Insulating joints shall be electrically tested before welding into the pipeline. The<br />

electrical conductance test shall be carried out using a Megger. Measurement <strong>of</strong><br />

the insulation resistance across the joints shall be approx. one (1) Mega Ohm.<br />

The tests shall be repeated after installation and welding <strong>of</strong> the joint into the<br />

pipeline to verify that the assembly is undamaged.<br />

13.0 WORKING SPREAD LIMITATIONS<br />

CONTRACTOR shall, in general, observe the following maximum distances<br />

between the working mainline spread:<br />

Between ROW grading, clearing and backfilling :40 Kms<br />

Between backfilling and final clean-up :15 Kms<br />

The above limitations do not apply to point spreads such as continuous rock<br />

blasting, river crossing, etc.<br />

Any deviations from the above shall require prior approval <strong>of</strong> COMPANY.<br />

COMPANY reserves the right to stop the work, in case the approved spread<br />

limitations are exceeded and CONTRACTOR shall not be paid any<br />

compensation for stoppage <strong>of</strong> work.<br />

14.0 CLEAN-UP AND RESTORATION OF RIGHT OF WAY<br />

14.1 CONTRACTOR shall restore the ROW and all sites used for the construction <strong>of</strong><br />

pipelines, water crossing and other structures in accordance with COMPANY's<br />

instructions, and deliver them to the satisfaction <strong>of</strong> COMPANY.