2.3 Monthly<br />

• Priced variations<br />

• Required materials for next month<br />

• Progress report for payment, safety report, report <strong>of</strong> accidents,<br />

security report, health and environment report, material balance,<br />

approved deviations.<br />

2.4 Further, Contractor shall supply (for approval if required to the Company<br />

with document such as but not limited :<br />

• Organogram for construction work.<br />

• Bio-data <strong>of</strong> key personnel (including foremen).<br />

• (Revised) list <strong>of</strong> address <strong>of</strong> personnel in particular <strong>of</strong> medical staff,<br />

safety and security <strong>of</strong>fers.<br />

• (Revised) list <strong>of</strong> approved coaters.<br />

• (Revised) list <strong>of</strong> approved sub-contractors.<br />

• Time schedule.<br />

• Acquired permits and/ or approvals from Authorities, if any.<br />

• Minutes <strong>of</strong> meeting with Company with comments, if any.<br />

• Material certificates, material receipt.<br />

• Guarantee from vendors and sub-contractor.<br />

• Calculations, temporary works, bouyance, blasting.<br />

\\Akjha\work contrac\standard TS for Pipe Line WC (Vol-<strong>II</strong>) MASTER FOLDER\69 documentation for pipeline construction\Specification for Documentation for PL Const - 69.doc<br />

Page 3 <strong>of</strong> 8

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!