sleeves shall be obtained without undue heating <strong>of</strong> existing pipe<br />

coating and providing due bonding between pipe, sleeve and pipe<br />

coating. A thermochrome paint shall be applied a an closure patch<br />

to indicate that sufficient heat/ temperature has been obtained. The<br />

joint coating shall have wear cone applied over the leading edge <strong>of</strong><br />

the sleeve and the clamping belt tightened over it.<br />

j) Application <strong>of</strong> Wear Cone - The leading edge will be given an extra<br />

wear cone. Start by heating the leading edge area <strong>of</strong> the main<br />

sleeve to 70 0 C. Wrap the leading edge sleeve over the transition<br />

Mill coating. Ensure that the closure is placed away from the main<br />

sleeve closure Shrink the leading edge sleeve.<br />

k) Application <strong>of</strong> Metal Belt - The metal belt shall be applied over the<br />

wear cone sleeve. The metal belt will be tightened using the<br />

strapper tool supplied by the manufacturer.<br />

l) Sufficient manpower working on opposite sides <strong>of</strong> each pipe joint<br />

are required for installation <strong>of</strong> the sleeve.<br />

m) The installed sleeve shall not be disturbed until the adhesive has<br />

solidified.<br />

5.0 INSPECTION<br />

5.1 For wraparound coating, a visual inspection shall be carried out for the<br />

following :<br />

- Mastic extrusion on either ends <strong>of</strong> the sleeves shall be examined<br />

- There shall be no sign <strong>of</strong> punctures or pinholes or bond failure.<br />

The external appearance <strong>of</strong> the sleeves shall be smooth, free <strong>of</strong><br />

dimples, air entrapment or void formation.<br />

- Weld bead pr<strong>of</strong>ile shall be visible over the sleeves.<br />

- The entire closure patch shall have changed colour uniformly.<br />

5.2 Holiday Inspection<br />

5.2.1 The Holiday Detector used shall be checked and calibrated daily with an<br />

accurate D.C. voltmeter. The detector electrode shall be in direct contact<br />

with the surface <strong>of</strong> coating to be inspected.<br />

5.2.2 The entire surface <strong>of</strong> the joint section shall be inspected by means <strong>of</strong> a full<br />

circle Holiday Detector approved by OWNER set to DC Voltage <strong>of</strong> at least<br />

25 kV for wraparound sleeves. Inspection <strong>of</strong> the heat shrink sleeve coating<br />

shall be conducted only after the joint has cooled below + 50°C.<br />

\\Akjha\work contrac\standard TS for Pipe Line WC (Vol-<strong>II</strong>) MASTER FOLDER\74 field joint for HDD crossing\Specification for FPJ Coating for HDD Crossing - 074-f.doc Page 11 <strong>of</strong> 14