MECON LIMITED<br />

REGD. OFF: RANCHI (BIHAR)<br />

PROCESS & PIPING<br />

DESIGN SECTION<br />

NEW DELHI<br />

TITLE PIPING FABRICATION AND<br />

ERECTION<br />

STANDARD SPECIFICATION<br />

SPECIFICATION NO. PAGE 19 OF 62<br />

MEC/S/05/62/06 REVISION 0<br />

ii. To supervise the welding procedure qualification.<br />

iii. To supervise the welder performance qualifications.<br />

c) Contractor shall intimate sufficiently in advance the commencement <strong>of</strong><br />

qualification tests welding works and acceptance tests, to enable the<br />

plant owner's inspector to be present to supervise them.<br />

1.13.2 Welding Procedure Qualifications<br />

a) Welding Procedure Qualification shall be carried out in accordance with<br />

the relevant requirements <strong>of</strong> API 1104/ ASME Sec-IX or other applicable<br />

codes and other job requirements by the contractor at his expense. The<br />

contractor shall submit the welding procedure specifications in format as<br />

per Exhibit-C (attached) immediately after the receipt <strong>of</strong> the order.<br />

b) COMPANY's inspector will review, check and approve the welding<br />

procedure submitted and shall release the procedure for procedure<br />

qualification tests. The procedure qualification test shall be carried out by<br />

the Contractor under field conditions at this own expense. A complete set<br />

<strong>of</strong> test results in format as per Exhibit-D (attached) shall be submitted to<br />

the COMPANY's inspector for approval immediately after completing the<br />

procedure qualification test and atleast 2 weeks before the<br />

commencement <strong>of</strong> actual work. Standard tests as specified in the code<br />

shall be carried out in all cases. In addition to these tests, other tests like<br />

radiography, macro/ micro examination, hardness testers, dye penetrant<br />

examination, Charpy V-notch etc. shall be carried out on specimens. It<br />

shall be the responsibility <strong>of</strong> the contractor to carry out all the tests<br />

required to the satisfaction <strong>of</strong> the COMPANY's Inspector. The destructive<br />

testing <strong>of</strong> welded joints shall be as per Annexure-2 and ASME Sec-IX.