MECON LIMITED<br />

REGD. OFF: RANCHI (BIHAR)<br />

PROCESS & PIPING<br />

DESIGN SECTION<br />

NEW DELHI<br />

STANDARD SPECIFICATION<br />

TITLE Flushing and Testing SPECIFICATION NO. PAGE 8 OF 9<br />

MEC/S/05/62/11 REVISION 0<br />

Prior to the start <strong>of</strong> any test or periodically during the field test programmes, all<br />

test gauges shall be calibrated using a standard dead weight gauge tester or<br />

other suitable approved testing apparatus. Any gauge having an incorrect zero<br />

reading or error <strong>of</strong> more than ± 2% <strong>of</strong> full scale range shall be discarded. The<br />

Engineer-in-charge shall check the accuracy <strong>of</strong> master pressure gauge used for<br />

calibration.<br />

4.4 Testing Pressure<br />

4.4.1 Hydrostatic Test<br />

All vents and other connections used as vents shall be kept open while filling the<br />

line with test fluid for complete removal <strong>of</strong> air. For pressurising and<br />

depressurising the system, temporary isolating valves shall be provided if valves,<br />

vents, drains do not exist in the system.<br />

Pressure shall be applied only after the system/line is ready and approved by<br />

the Engineer-in-charge.<br />

Pressure shall be applied by means <strong>of</strong> a suitable test pump or other pressure<br />

source which shall be isolated from the system as the desired test pressure is<br />

reached and stabilised in the system.<br />

A pressure gauge shall be provided at the pump discharge for guiding the<br />

system to the required pressure.<br />

The pump shall be attended constantly during the test by an authorised person.<br />

The pump shall be isolated from the system wherever the pump is to be left<br />

unattended.<br />

Test pressure shall be maintained for a sufficient length <strong>of</strong> time to permit<br />

through inspection <strong>of</strong> all joints for leakage or signs <strong>of</strong> failure. Any joint found<br />

leaking during a pressure test, shall be re-tested to the specified pressure after<br />

repair. Test period shall be maintained for a minimum <strong>of</strong> three hours.<br />

The pump and the piping system to be tested are to be provided with separate<br />

pressure indicating test gauges. There gauges are to be checked by the<br />

standard test gauge before each pressure test.