MECON LIMITED<br />

REGD. OFF : RANCHI (BIHAR)<br />

Document6<br />

PROCESS & PIPING<br />

DESIGN SECTION<br />

NEW DELHI<br />

TITLE MAINLINE CONSTRUCTION<br />

(ONSHORE)<br />

STANDARD SPECIFICATION<br />

SPECIFICATION NO. PAGE 34 OF 53<br />

MEC/S/05/62/01 REVISION A<br />

At every seven meters along the trench sand/earth filled bags shall be placed<br />

between the parallel pipelines so as to ensure maintenance <strong>of</strong> the minimum<br />

stipulated distance between the parallel lines.<br />

9.2 Overhead Sections and Sections in Tunnel<br />

9.2.1 The following works shall be completed before proceeding with the assembly<br />

and laying <strong>of</strong> overhead pipelines :<br />

- Construction <strong>of</strong> the pipe support structures or <strong>of</strong> mounts on supports.<br />

- Paints and/or coating <strong>of</strong> the pipework, as indicated in the engineering<br />

specification.<br />

9.2.2 The erection <strong>of</strong> the supports shall be carried out taking care that the elevation<br />

and alignment is in accordance with the drawings.<br />

In the case <strong>of</strong> metal work supports, prefabrication and/or assembly shall take<br />

into account the maximum allowed free span and the supports shall not interfere<br />

with the pipeline welds.<br />

9.2.3 In case roller supports are used, the roller shall be lubricated, then checked for<br />

smooth rotation and, in case <strong>of</strong> seizure, the defect shall be repaired or roller<br />

shall be replaced. In the case <strong>of</strong> overhead section where the pipeline is slanting,<br />

the alignment <strong>of</strong> the end supports shall be made after placing the pipeline in<br />

position. Before installation <strong>of</strong> the pipe section, all the rollers shall be perfectly<br />

centered acting on the seat <strong>of</strong> the support plates.<br />

The above alignment operations shall be carried out before connecting the<br />

overhead section with the ends <strong>of</strong> the buried section.<br />

9.2.4 Lifting, moving and laying <strong>of</strong> the pipeline shall be carried out in accordance with<br />

the provisions <strong>of</strong> clause 9.1.5.<br />

An insulation sheet shall be installed to isolate the pipe from the support or<br />

support from the earth.<br />

The sheet shall be hard polyethylene at least 5mm thick.<br />

It shall extend at least to 1cm outside the saddles or clamps.