TITLE Flushing and Testing SPECIFICATION NO. PAGE 4 OF 9<br />

4.0 Testing<br />

MEC/S/05/62/11 REVISION 0<br />

Records in triplicate shall be prepared and submitted by the Contractor for each<br />

piping system for the flushing done in the pr<strong>of</strong>orma in Exhibit F.<br />

4.1 Extent <strong>of</strong> testing<br />

With the exclusion <strong>of</strong> instrumentation. piping system fabricated or assembled in<br />

the field shall be tested irrespective <strong>of</strong> whether or not they have been pressure<br />

tested prior to site welding <strong>of</strong> fabrication.<br />

To facilitate the testing <strong>of</strong> piping systems, vessels and other equipments may be<br />

included in the system with the prior approval <strong>of</strong> Engineer-in-charge, if the test<br />

pressure specified is equal to or less than that for the vessels and other<br />

equipments.<br />

Pumps, compressors and other votary equipments shall not be subjected to field<br />

test pressures.<br />

Lines which are directly open to atmosphere such as vents, drains, safety<br />

valves, discharge need not be tested, but all joints shall be visually inspected<br />

wherever necessary such lines shall be tested by continuous flow <strong>of</strong> fluid to<br />

eliminate the possibility <strong>of</strong> blockage. However, such lines if provided with block<br />

valve shall be pressure tested upto the first block valve.<br />

Seats <strong>of</strong> all vales shall not be subjected to a pressure in excess <strong>of</strong> the maximum<br />

cold welding pressure <strong>of</strong> the valve. Test pressure applied to vales shall not be<br />

grater than the manufacturer is recommendation nor less than that required by<br />

the applicable code. Where desirable set pressure is less than test pressure,<br />

test shall be made through an open valve.<br />

Instruments in the system to be tested, shall be excluded from the test by<br />

isolation or removal, unless approved otherwise by the Engineer-in-charge.<br />

Restrictions which interfere with filling, venting and drawing such as orifice plates<br />

etc. shall not be installed unless testing is complete.<br />

Control valves shall not be included in the test system. Where by-passes are<br />

provided test shall be performed through the by-pass end/or necessary spool<br />

shall be used in place <strong>of</strong> the control valve.