1.0 INTENT<br />

2.0 OBJECT<strong>IV</strong>E<br />

SPECIFICATION FOR CALIPER PIGGING<br />

The intent <strong>of</strong> this specification is to setforth the requirements <strong>of</strong> the<br />

caliper pigging. The specification is not intended to be all-inclusive and the<br />

use <strong>of</strong> this specification will not absolve the contractor <strong>of</strong> his responsibility<br />

<strong>of</strong> generating valid, interpretable and physically verifiable data.<br />

The objective <strong>of</strong> the present pigging programme to access the internal<br />

geometry <strong>of</strong> the following pipelines and detect significant geometry<br />

defects if any, which may affect safe operation <strong>of</strong> the pipeline.<br />

The relevant technical specifications <strong>of</strong> the pipeline including launcher and<br />

receiver details in the Annexure.<br />

3.0 SCOPE OF WORK<br />

To achieve the above objective, contractors SCOPE OF WORK includes<br />

running <strong>of</strong> adequate numbers <strong>of</strong> foam pigs, cleaning pigs (magnet, brush,<br />

commination <strong>of</strong> brush and magnet, scraper, pin wheel etc.), gauge pig<br />

and caliper pig.<br />

Further the scope <strong>of</strong> work comprises supply <strong>of</strong> skilled personnel, all<br />

equipment e.g. foam pigs cleaning pigs, gauging pig, caliper pigs, pig<br />

locating and pig tracking devices, spares consumables, communication<br />

and transportation including their mobilisation and demobilisation. It is<br />

expressly understood that this do not limit the scope <strong>of</strong> work <strong>of</strong> the<br />

CONTRACTOR in any way. The quantities to be mobilized for different<br />

equipment (different types <strong>of</strong> pigs pig tracking device, marker device)<br />

accessories, spare and consumables need to be carefully evaluate by the<br />

CONTRACTOR taking in to the consideration that caliper pigging <strong>of</strong> various<br />

\\Akjha\work contrac\standard TS for Pipe Line WC (Vol-<strong>II</strong>) MASTER FOLDER\70 caliper pigging spec\Specification for Caliper Pigging - 70.doc Page 1 <strong>of</strong> 9