D060<br />

Edward W. Chance Reserve Hydr. Rest.<br />

Construction Complete 9/30/07 6/1/<strong>10</strong><br />

Status As Of: June 22, 2009<br />

The consultant completed the final restoration plan which identified three distinct areas where minor modifications to the<br />

ditch network will result in rehydration of degraded wetlands. ACTION TO DATE: On-time. King Engineering, the<br />

District's environmental consultant on the project is working on the model verification of the site hydrology. This is proving<br />

to be more time consuming than originally anticipated. There are however certain elements of the project that can be<br />

accomplished by permit exemption. Part of the construction plan is to plug several upland agricultural ditches that are no<br />

longer contributing surface water to Gilley Creek. Instead of incorporating this into the ERP, the District may be able to<br />

apply for and receive a de minimis exemptions from the Florida Department of Environmental Protection (FDEP) for<br />

minor activities such as this. If FDEP grants the District a De minimis exemption for this, it will allow us to begin<br />

construction and accomplish a portion of the project. District staff will begin negotiating with FDEP for the exemption. If<br />

FDEP agrees that this work is minor, District crews could accomplish the construction by the end of the year if site<br />

conditions permit.<br />