10.12.2012 Views

MANASOTA & PEACE RIVER BBDs Meeting Notebook 10-21-09.docx

MANASOTA & PEACE RIVER BBDs Meeting Notebook 10-21-09.docx

MANASOTA & PEACE RIVER BBDs Meeting Notebook 10-21-09.docx

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

H051<br />

PR/MRWSA Reg Integ Loop Sys Phase 2 Interconnect<br />

Project Type WS&R Dev.<br />

AOR(s)<br />

Water Supply<br />

Basin(s) General Fund (District), Peace River, Manasota<br />

Cooperator(s)<br />

Project Manager FERGUSON, JOHN<br />

Task Manager(s)<br />

Status Ongoing<br />

Peace River/Manasota Regional Water Supply Auth.<br />

ARMSTRONG, BRIAN<br />

Description<br />

The Regional Integrated Loop System project is a series of transmission pipelines that will be developed to regionally<br />

transfer and deliver water from existing and future alternative supplies to demand centers within the Peace<br />

River/Manasota Regional Water Supply Authority's four county region. The Phase II Interconnect project is a<br />

component of the Regional Integrated Loop System that will provide needed regional transmission capacity between<br />

the Peace River Facility and the City of North Port. The transmission line will be a 36-to-48 inch diameter pipeline<br />

extending approximately 5.5 miles from the Peace River Facility, generally along the existing 36-inch regional<br />

transmission main (RTM) corridor to Serris Boulevard, where it will interconnect with the City of North Port's<br />

transmission/distribution system. In addition to serving the City of North Port, Phase II provides back-up capacity to the<br />

existing 36-inch RTM, and comprises a critical segment for the extension of future regional transmission capacity to<br />

the City of North Port's Myakkahatchee Creek Water Treatment Facility, the Englewood Water District treatment<br />

facilities, and the Carlton Water Treatment Facility.<br />

Benefits<br />

The initial segment of the Phase 2 Interconnect will allow the City of North Port to receive additional water from the<br />

Authority's ongoing expansion project. The City currently requires this project to transmit the quantities of water they<br />

are contracted to purchase from the Authority in FY2012. Development of additional segments will further integrate<br />

regional resources; maximize surface water for public supply; provide rotational capacity and the ability to rest sources;<br />

provide for reserve capacity for emergency transfers; provide alternatives to the development of groundwater in the<br />

Southern Water Use Caution Area (SWUCA); and better match supply, demand and financial investment on a regional<br />

basis. The use of alternative sources with the maximization of surface water for public supply is consistent with the<br />

District's Regional Water Supply Plan.<br />

Costs<br />

The total estimated cost for the H051 Phase 2 Interconnect is $15,400,000 with the requested District share being<br />

$7,700,000. The District funding will be divided between the Governing Board, $3,850,000 (50%); Manasota Basin,<br />

$2,8<strong>10</strong>,00 (36.5%); and the Peace River Basin, $1,039,500 (13.5%). District funding in FY20<strong>10</strong> is anticipated to be:<br />

General fund $1,500,000; Manasota $500,000; Peace River $200,000; for a total of $2,200,000.<br />

The Funding table below shows funds that were budgeted in "FY2007" and "FY2008" and "Cumulative Transfers".<br />

Those funds lapsed at the end of their fiscal years, as the project was not pursued at those times. A negative<br />

adjustment is made under "prior funding" to show the actual total funding.<br />

The long-term project cost of all additional Phase 2 components for joining the Englewood Water District, City of<br />

Venice, and the Carlton WTP has been estimated at $<strong>10</strong>6,378,<strong>21</strong>7.<br />

Additional Information<br />

The Loop Feasibility/Routing Study was authorized by the Authority in May 2005 and the report was issued in June<br />

2006. The Feasibility/Routing Study identified the preferred loop pipeline routing, environmental impacts, major<br />

connection points, preliminary pipe sizing, proposed schedule of project phasing, and time frames for construction.<br />

The Study's recommended Phase 2 route connects the Peace River Water Treatment Plant with the Myakkahatchee<br />

Creek Water Treatment Plant and then branches into two segments. The one segment loops northwest to Sarasota<br />

County's Carlton Water Treatment Facility, and the other segment runs southwest and connects to the public water<br />

systems of the Englewood Water District and the City of Venice.<br />

In August 2007, the Authority Board approved the first work order for Phase 2 of the Regional Loop System and<br />

issued a notice to proceed. In December 2007, the Authority's consultant released a preliminary design report for the<br />

Phase 2. In May 2008, the Authority chose to postpone the project in favor of an alternate connection between North<br />

Port's system near the Snover Waterway and the existing regional line connecting the Carlton and Peace River WTPs.<br />

As a result, the District reallocated the FY2007 and FY2008 funds towards other projects.<br />

After much discussion between the City of North Port, Sarasota County, and the Authority over shared capacities, the<br />

Snover Waterway connection was considered insufficient to meet all the partners' combined needs. In November<br />

2008, the Authority revised a shorter version the Phase 2 project, which calls for a segment between the Peace River<br />

WTP and the North Port's Serris Blvd connection. The pipeline would be the length needed to deliver an increased<br />

capacity to the City, but would retain the greater transmission capacity needed for future extensions. In February 2009,<br />

020 - Peace River Basin 202

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!