W796<br />

Chain of Lakes Water Quality Management Plan<br />

Critical Project Milestones Projected Amended Actual<br />

1. Contract Devlopment and Execution<br />

Contract Executed 12/31/05 3/31/06 9/15/06<br />

Notice to Proceed 1/6/06 3/31/06 9/22/06<br />

Amendment Executed 12/26/08 2/4/09 2/4/09<br />

2. Project Phases<br />

Completion of Phase I - Evaluation of Existing Information 7/1/07 11/1/07 1/12/08<br />

Completion of Phase II - Evaluation of Existing Conditions 3/1/08 2/<strong>10</strong>/<strong>10</strong><br />

Completion of Phase III - Preparation of Water Quality Master Plan 11/1/08 7/15/<strong>10</strong><br />

3. Agreement Expiration Date<br />

Agreement to expire 12/31/08 12/31/<strong>10</strong><br />

4. Project Completion<br />

Project Completion 12/31/09 8/31/<strong>10</strong><br />

Status As Of: September 09, 2009<br />

The agreement with the City was executed September 15, 2006. The consultant began Phase I tasks in June 2007. In<br />

Phase I of the project, the Consultant evaluated existing information which includes collection, review and compiling of<br />

existing surface water, groundwater, stormwater and sediment quality and quantity information, data and studies to<br />

achieve a thorough understanding of available information and science in the Winter Haven Chain of Lakes. Phase I<br />

Data Evaluation has been completed and a report has been received. A coordination meeting was held during which the<br />

FDEP requested that Phase II of this project be put on hold until additional data collection by the FDEP is completed. The<br />

result of the additional data collection by the FDEP was a Pre-BMAP Report, which was submitted to the City and the<br />

District by the FDEP's consultant to be incorporated into this project's efforts. This information will be used in Phase II of<br />

the project. A no-cost time extension 1st Amendment has been executed with an expiration date of December 31, 20<strong>10</strong>.<br />