K269<br />

Sarasota Co. - N. Sarasota Co. Reclaimed Water ASRs<br />

Project Type Cooperative Funding<br />

AOR(s)<br />

Water Supply, Water Quality<br />

Basin(s) Manasota<br />

Cooperator(s)<br />

Sarasota County<br />

Project Manager MCGOOKEY, SCOTT<br />

Task Manager(s)<br />

Status Ongoing<br />

Description<br />

This project consists of the design, permitting, and construction of three 1.2 mgd reclaimed water aquifer storage and<br />

recovery (ASR) wells with ultra-violet (UV) disinfection. These ASRs will be constructed at the County's Central County<br />

Wastewater Treatment Facility (WWTF). The ASRs will provide wet weather storage for the County's Northern<br />

Regional Reuse System, consisting of four interconnected county WWTFs's and a interconnection with the City of<br />

Sarasota's Reuse System.<br />

Benefits<br />

The project will provide storage of approximately 1,200,000 gpd for 120 days or 144 million gallons per year for each of<br />

three proposed ASR wells for a total of 432 million gallons per year stored. This will yield a flow of approximately<br />

888,000 gpd of reclaimed water to offset existing ground-water withdrawals and potable service and better serve<br />

existing reclaimed water users such as Palmer Ranch, Manor Care of Boynton Beach, Plaza Oaks, Silver Oak, and the<br />

Hamptons Development.<br />

Costs<br />

The total project cost is estimated to be $6,443,546, and the District's share is requested to be 50 percent, or<br />

$3,2<strong>21</strong>,773. The Manasota Basin has funded $2,011,743 so far, between FY2000 and FY2007, and the WPSTF<br />

provided $164,864 in FY2006/7, for a total of $2,176,607 already budgeted for the project. The Manasota Basin will<br />

fund $1,127,598 in future years. The cost, amortized at 8 percent over 30 years, is $1.75 per thousand gallons of<br />

traditional water offset. Any additional funds are for staff time. The future funds identified for the project are contingent<br />

upon approval of such amounts by the District Governing and Basin Boards in the annual budget(s).<br />

Additional Information<br />

This is a multi-year project that will expand Sarasota County's reclaimed water system by providing wet weather<br />

storage for the interconnected reclaimed water systems of the Sarasota County and City of Sarasota. This regional<br />

system has five wastewater treatment plants with a permitted capacity of 18.5 mgd and a reuse flow of 5.4 mgd that<br />

are now interconnected. This wet weather storage will increase the system's efficiency. Cost history: The original<br />

project was submitted to the SWFWMD in 1998 and was approved for multi-year funding beginning in FY2000 and<br />

ending in FY2005 with a total cost of $3,030,000. Following a lengthy hearing resulting in DEP issuing a permit to<br />

proceed with construction of the first of three ASR wells, a first amendment was approved in 2006, which increased<br />

the total cost and apportioned the District's share as follows: Cost Breakout: FY2000 = $<strong>10</strong>0,000 FY2001 = $550,000<br />

FY2002 = $390,000 FY2003 = $405,000 FY2006 = $311,607 ($286,743 ad valorem $24,864 WPSTF) FY2007 =<br />

$420,000 ($280,000 ad valorem $140,000 WPSTF) FY20<strong>10</strong> = $350,000 FY2011 = $350,000 and FY2012 = $427,598.<br />

The County has updated the costs, revised the timeline and also determined that split flow UV disinfection is needed<br />

for this project to ensure that water quality can consistently meet drinking water standards prior to injection into the<br />

aquifer. An added benefit of installing UV disinfection is documented effectiveness in treating water borne pathogens<br />

that are not amenable to chlorine disinfection. The cost of the UV disinfection system for each well is estimated at<br />

$580,000. Of the total project cost of $6,443,546, approximately 83 percent ($5,320,247) is expected to be needed for<br />

construction, and the remainder ($1,123,299) for design and administration.<br />