L028<br />

(Completed) Englewood Lemon Bay High School Reuse Extension<br />

Contract Termination <strong>10</strong>/1/06 12/31/08 8/22/08<br />

Status As Of: August 26, 2008<br />

Damage to the school from hurricane Wilma has delayed this project. EWD met with the school board on January <strong>10</strong>,<br />

2006 and approved the agreement with the EWD to utilize reclaimed water at the schools athletic fields. The project<br />

design was awarded to Giffels-Webster Engineers on February 28, 2006. Design is now complete. Base maps have<br />

been prepared and the route of the pipe has been approved by Charlotte County Parks Department. Permits have<br />

been processed. A pre-bid meeting was July 17th, 2007 with the bid opening on August 7, 2007. The low bid was<br />

submitted by General Contracting. Notice to Proceed and all easements are secured. Construction began March 5,<br />

2008. On April 23, 2008 the construction was substantially complete. The connection at the school has now been made<br />

and they are receiving reclaimed water. A no-cost time extension amendment was executed March 22, 2006. The<br />

Peace Basin Board encumbered $150,000 in its FY2004 budget. To date, the District has reimbursed EWD $127,240.<br />

This project is now complete.<br />