Evaluation and Demonstration of Soil Moisture Based On-demand<br />

Irrigation Controllers for Vegetable P<br />

Prior Cumulative FY 2009 FY20<strong>10</strong><br />

Funding Transfers Funding Funding<br />

District Budgeted - Ad Valorem Based<br />

Revenue<br />

<strong>10</strong>7,175 0 35,725<br />

0<br />

0<strong>21</strong> Manasota Basin 0 142,900<br />

Total:<br />

Future<br />

Funding<br />

Total<br />

Funding<br />

$142,900<br />

Critical Project Milestones Projected Amended Actual<br />

Agreement to Contracts 8/1/05 8/1/05<br />

Agreement to Cooperator 9/1/05 9/1/05<br />

District Executes Agreement <strong>10</strong>/1/05 <strong>10</strong>/1/05<br />

Notice to Proceed 11/1/05 11/1/05<br />

Basin Board Notification 12/1/05 12/1/05<br />

Governing Board Notification 12/1/05 12/1/05<br />

Year 1. Data Collection 12/1/06 12/31/06<br />

Year 2. Data Collection 12/1/07 12/31/07<br />

Year 3. Data Collection 12/1/08<br />

Completion Report 12/1/09<br />

Project Ends 3/1/<strong>10</strong><br />

Status As Of: August 27, 2009<br />

9/15/2005 - Developing final scope of work. 12/30/2005 - Mailed Agreement to Cooperator. 1/11/06 - Cooperator<br />

reviewing agreement. 2/22/06 - Mailed notice to proceed. 3/2/2006 - Mobilizing equipment. 4/17/2006 - Instrumenting<br />

site. 6/5/2006 - reviewed task 1 and 2. Normal research issues (calibrating controls) project continuing as planned.<br />

7/18/06 - Process payment. 8/15/2006 - Dormant for summer. <strong>10</strong>/12/2006 - Data collection continuing as planned.<br />

12/4/2006 - Dormant for winter. 2/28/2007 - Planted crop data collection continuing as planned. 5/1/2007 - Data<br />

collection continuing as planned. 67/26/2007 - Data collection continuing as planned. 8/31/2007 - Looking for cooperator<br />

in Manasota Basin. The extension Agent has retired and there are problems finding a cooperator. 1/2/2008 - Continuing<br />

to look for cooperator. Might have found site, but could have problems with irrigation system. 2/29/2008 - May have found<br />

cooperator, working out details. 5/1/2008 - Working with cooperator in Manasota watershed. 7/1/2008 - Field testing<br />

equipment. 9/1/2007 - Data collection on commerical growers site, continuing as planned 11/1/2008 - 9/1/2007 - Data<br />

collection on commerical growers site, continuing as planned. 12/6/2008 - Palmetto growers event. 3/6/2009 - waiting for<br />

report 5/18/2009 - waiting for report 6/<strong>10</strong>/2009 - waiting for report 9/1/2009 - Statring data collection, project continuing<br />

as planned.<br />