Aqua Utilities Reuse Transmission - Eastern Lakewood Ranch<br />

Complete Construction: 11/1/09 8/31/09<br />

Status As Of: August 31, 2009<br />

Processing the agreement was initially delayed due to funding considerations concerning WPSTF funds and acquisition<br />

of the required insurance documentation. The agreement with Aqua Utilities was executed on March 24, 2008. DMK<br />

Associates was selected to design the project and has completed the field study and design work on the transmission<br />

line and pump station. The construction contract was awarded to the low bidder, Woodruff and Sons, Inc.. Construction<br />

on the transmission line began in January 2009 and all the 12 inch and 20 inch reuse pipeline was installed as of April<br />

16, 2009. The concrete pads, pumps and controls were installed the end of July. The system has been tested and is<br />

substantially complete. Awaitnig final walk-through and development of punch list. First invoice is being processed for<br />

payment. The District's entire funding commitment has been encumbered, of which to date $0 has been reimbursed.<br />

This project is consistent with Governor Crist's Accelerate Florida Initiative to stimulate Florida's economy.<br />

Action-to-date: Ontime.<br />

0<strong>21</strong> - Manasota Basin 3<strong>21</strong>