K253<br />

Manatee - Imp. BMPs Wares Creek<br />

project. Furthermore, the Basin Board, at its August 2005 meeting budgeted $3,000,000 for FY2006 for this project.<br />

For FY2007 the county sought additional funding of $2,000,000 to be applied towards the land acquisition and<br />

easement expenses and the non-federal share of construction including dredging of the lower Wares Creek between<br />

the Manatee Avenue Bridge and the Manatee River. A new cooperative funding expenditure agreement has been<br />

developed to incorporate the change in scope and the additional funds. The District is also co-funding project L200<br />

with the City of Bradenton which will replace 4 bridges across Wares Creek within the city limits and will provide<br />

additional flow capacity within the stream banks.<br />

Prior<br />

Funding<br />

Cumulative FY 2009 FY20<strong>10</strong><br />

Transfers Funding Funding<br />

District Budgeted - Ad Valorem Based<br />

Revenue<br />

0<strong>21</strong> Manasota Basin <strong>10</strong>,953,357 0 4,170 3,198 3,337,464 14,298,189<br />

Project Funds Not Budgeted by the<br />

District<br />

Florida DEP (Bradenton) 0 0 500,000<br />

0<br />

0 500,000<br />

Florida DEP (Manatee County) 1,650,000 0 0<br />

0<br />

0 1,650,000<br />

Manatee County <strong>10</strong>,916,536 0 2,000,000 1,337,464<br />

0 14,254,000<br />

U.S. Army Corps of Engineers 0 0 24,507,500<br />

0<br />

0 24,507,500<br />

Total:<br />

Future<br />

Funding<br />

Total<br />

Funding<br />

$55,209,689<br />

Critical Project Milestones Projected Amended Actual<br />

1. Critical Project Milestones<br />

District signage will be provided on all construction signs. 12/1/02<br />

2. 5% Construction<br />

District Agreement Execution 5/31/00 5/31/00<br />

USACE Execution of the Memorandum of Agreement 1/31/01<br />

Permitted Construction Drawings 3/15/01<br />

Begin Construction 12/1/02<br />

Contract Termination 3/31/05 3/31/06<br />

3. Rights-of-Way Acquisitions<br />

Draft Agreement to Management Services 12/15/00 1/18/01<br />

Survey Work Began 12/18/00 12/18/00<br />

Draft Agreement Returned from Management Services 1/31/01 3/12/01<br />

Basin Board Approval of Agreement 2/<strong>21</strong>/01 2/<strong>21</strong>/01<br />

Governing Board Approval of Agreement 2/26/01 2/26/01<br />

Contract Executed 4/15/01 8/23/01<br />

Notice to Proceed 9/5/01 <strong>10</strong>/2/01<br />

4. FY 2005 Funding<br />

Draft Agreement to Management Services 6/30/04 6/30/04<br />

Draft Agreement Returned from Management Services 7/15/04 7/15/04<br />

Contract Executed 8/15/04 <strong>10</strong>/28/04<br />

Notice to Proceed 8/16/04 11/1/04<br />

Project Complete 12/30/04 12/31/06<br />

Contract Termination 12/31/04 12/31/06<br />

5. New Agreement (FY 2006/2007/2008 funding)<br />

Contract Executed 3/31/07 3/6/08<br />

Notice to Proceed 3/31/07 3/7/08<br />

Funds Encumbered 4/15/07 3/24/08<br />

Project Complete 12/31/12<br />

0<strong>21</strong> - Manasota Basin 248

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!