Longboat Key Backup Potable Water Supply Interconnect<br />

Basin Board Notification of Agreement Execution 6/15/05 <strong>10</strong>/12/05 <strong>10</strong>/12/05<br />

Signage Erected 7/31/06 12/<strong>10</strong>/07 4/30/08<br />

Commence Construction 7/31/06 11/30/07 12/<strong>10</strong>/07<br />

Project Complete 12/31/07 12/31/09<br />

Contract Close-out 12/31/08 3/31/<strong>10</strong><br />

Status As Of: August 28, 2009<br />

A total of $1,000,000 has been budgeted for the project through FY2008. Construction began (December <strong>10</strong>, 2007). The<br />

first invoice was received in January 2009 and was reviewed by the District's project manager. Additional backup was<br />

requested for the invoice on March 18, 2009, but it has not been received. The Longboat Key project manager indicated<br />

they are working on an invoice resubmittal package. Construction completion has been delayed to December 31, 2009<br />

because of permitting complications and slow progress on the chemical treatment system and metering compound. The<br />

contract close-out date has been affected and an agreement to extend the contract period was executed and mailed to<br />

the Cooperator on February 20, 2009.<br />

Pipeline Design, Permitting, and Construction The pipeline design was completed. The Town forwarded the <strong>10</strong>0 percent<br />

design level plans and technical specifications to the District on July 26, 2007. Staff was notified that the final design of<br />

the pipeline alignment differs slightly from the 60 percent design level because of permitting issues.<br />

A Department of Health permit was received on March 5, 2007 and a Florida Department of Transportation permit was<br />

received on April 23, 2007. The Town submitted a Joint Application Environmental Resource Permit (ERP)/Dredge and<br />

Fill/Submerged Land Lease, which includes permits required by the District, Army Corps of Engineers (ACOE), and the<br />

Florida Department of Environmental Protection (FDEP). The District issued an exemption to the ERP portion of the<br />

permit on December 20, 2006, and the ACOE issued a Regional General Permit on March 8, 2007 for dredge and fill<br />

activities. The Sovereign Submerged Lands Lease was fully executed on August 9, 2007. A copy of the fully executed<br />

and recorded easement was returned to the FDEP Department of State Lands on August 27, 2007. The City of Sarasota<br />

entered an access agreement with the contractor on April 3, 2008. The District's Sarasota Regulation Department<br />

accepted the planned pipe transport alternative on April <strong>10</strong>, 2008. The final pipeline alignment did fall outside the<br />

Sovereign Submerged Land Lease easement in a small area. The Town and Engineer adjusted the easement<br />

description and lease language, and SWFWMD forwarded the updated survey to the FDEP on April 22, 2009. The Town<br />

received an updated land lease easement from the FDEP on June 5, 2009. The full execution was recorded at the<br />

Sarasota County Clerk of Court on July 31, 2009.<br />

The District received the bid set plans and technical specifications on August 2, 2007. The bid was awarded to Expertech<br />

Network Installation (US) Inc. and notice to proceed was issued for a December <strong>10</strong>, 2007 commencement date. The<br />

contractor mobilized on January 18, 2008 and began drilling on January 30, 2008. Drilling was slower than originally<br />

anticipated by the contractor due to equipment issues and the apparent presence of rock. Drilling of the pipeline hole was<br />

completed May 12, 2008, and the pipeline was pulled under New Pass into place on May 14, 2008. Pressure testing and<br />

chlorination of the pipe was conducted the week of May 26, 2008. The contractor performed confirmation surveying on<br />

August 26-27, 2008 and September 5-6, 2008 and was found to be acceptable on October 13, 2008 by the consulting<br />

engineer, CDM. On November <strong>10</strong>, 2008, CDM approved the contractor's first request for payment covering work from<br />

March 1, 2008 to July 30, 2008. On June 23, 2009, the Expertech Florida office was closed and the project data was<br />

transferred to the Expertech Canada office. A final pay request for the construction was received on August 17, 2009.<br />

South Key Station No. 2 Design and Permitting A District Environmental Resource Notice General Permit was approved<br />

on January 16, 2008. An application for a Specific Permit to construct potable water system components was received<br />

from the Department of Health on February 25, 2008. A Site Plan Exemption wasreceived from the Town of Longboat<br />

Key Planning, Zoning, and Building Department on June <strong>10</strong>, 2008. The South Key Station No. 2 Improvements project<br />

was advertised for bid on June 24, 2008. The bid opened August 6, 2008, was awarded August <strong>21</strong>, 2008, and was<br />

executed October 20, 2008. The preconstruction conference was held on November 4, 2008 and the Notice to Proceed<br />

was issued on November 11, 2008. The contractor mobilized on January 12, 2009. Construction on the meter compound<br />

has commenced and is 40% complete. The chemical equipment should be installed in September 2009 and site<br />

preparations have commenced.<br />

ACTION-TO-DATE: Delayed. An information request concerning the Accelerate Florida Program was mailed to the<br />

cooperator on October 15, 2008. The District's project manager followed up with an email on January 16, 2009 and a<br />

phone call on February 9, 2009. The Town responded with a letter dated February 12, 2009 that stated the following:<br />

"The project is currently in construction. The drilling portion of the project is completed and final billing should be received<br />

soon. The chemical blending and meter compound portions of the project are on the horizon. The contractor is in shop<br />

drawing submittal phase with those portions of the project. We are working with the contractor to get those last few<br />

pieces of the project completed as soon as practical without hindering portions of the project that are not included in the<br />

L230 project."<br />