L640<br />

(Completed) Punta Gorda Reuse Feasibility Study<br />

Project Type Cooperative Funding<br />

AOR(s)<br />

Water Supply, Water Quality<br />

Basin(s) Peace River<br />

Cooperator(s)<br />

Punta Gorda<br />

Project Manager BADER, TAMMY<br />

Task Manager(s)<br />

Status Completed<br />

Description<br />

This project consists of a reuse feasibility study to identify the technical and financial elements of a reclaimed water<br />

system. The City of Punta Gorda owns and operates a 4 mgd wastewater treatment plant, and currently disposes all of<br />

its reclaimed water via a deep injection well. The feasibility study would consider a reclaimed water system to treat and<br />

deliver reclaimed wastewater for beneficial use as landscape irrigation.<br />

Benefits<br />

Upon completion of this project, the City will have a reuse feasibility study considering a reclaimed water system to<br />

treat and deliver reclaimed wastewater for beneficial use.<br />

Costs<br />

The total estimated cost of this project is $250,000, of which the Peace River Basin is requested to fund 50 percent, or<br />

$125,000. Funding in the amount of $125,000 has been budgeted for FY2007.<br />

Additional Information<br />

The City wants to develop a reclaimed water system that will assist in achieving goals of the SWUCA, reducing<br />

demands from the public water system and reducing demands from groundwater used for irrigation wells.<br />

Prior<br />

Funding<br />

Cumulative FY 2009 FY20<strong>10</strong><br />

Transfers Funding Funding<br />

District Budgeted - Ad Valorem Based<br />

Revenue<br />

020 Peace River Basin 128,988 0 1,299<br />

0<br />

0 130,287<br />

Project Funds Not Budgeted by the<br />

District<br />

Punta Gorda 125,000 0 0<br />

0<br />

0 125,000<br />

Total:<br />

Future<br />

Funding<br />

Total<br />

Funding<br />

$255,287<br />

Critical Project Milestones Projected Amended Actual<br />

Draft Project Agreement <strong>10</strong>/31/06 9/1/06<br />

Execute Project Agreement 12/31/06 12/20/06<br />

Begin Feasibility Study 12/31/06 1/5/07<br />

Complete Feasibility Study 5/31/07 12/31/07 1/15/08<br />

Project Close-out 12/31/08 4/30/08<br />

Status As Of: June 06, 2008<br />

A Cooperative Funding Agreement was executed on December 20, 2006. Carollo Engineers was given notice to proceed<br />

on January 5, 2007 and submitted the draft feasibility study on July 5, 2007. Staff provided comments and suggested<br />

changes to the City and engineers on July 24, 2007. The City requested an extension to December 31, 2007 to<br />

incorporate comments and finalize the feasibility study. The City submitted the final reuse feasibility study on January 15,<br />

2008 to complete this project. The City has submitted a request for reimbursement in the amount of $61,480 and staff<br />

has forwarded a G-2 and G-3 to Finance. To date, $125,000 has been encumbered, of which $61,480 has been<br />

reimbursed.<br />

020 - Peace River Basin 277