L608<br />

Palmetto Reclaimed Water ASR<br />

Critical Project Milestones Projected Amended Actual<br />

Draft Agreement to Contract Administration: 9/30/06 9/30/06<br />

Agreement Executed / Notice to Proceed: 11/30/06 1/24/07<br />

Start construction of reclaimed water ASR: 9/1/07 3/5/08<br />

Complete construction of reclaimed water ASR: 8/30/<strong>10</strong><br />

Start Cycle Testing: 9/1/<strong>10</strong><br />

Complete Cycle Testing & Obtain Operational Permit: 12/31/<strong>10</strong><br />

Final Invoice: 4/30/11<br />

Contract Termination: 6/30/11<br />

Status As Of: August 25, 2009<br />

The agreement with the City was executed on January 24, 2007. The public hearing for the draft FDEP ASR construction<br />

permit was held on January 23, 2007. The FDEP ASR Construction Permit was issued in April 2007. The City of<br />

Palmetto has agreed with the District to construct the Storage Zone Monitor Well (SZMW) / Exploratory Well as the first<br />

well. This will allow us to gather information about the target aquifer, a drinking water aquifer, and a lower aquifer to<br />

determine if it's suitable for ASR development. If that lower zone is not a drinking water aquifer, and it's suitable for ASR,<br />

it may allow us to bypass the arsenic requirements for ASRs in the drinking water aquifers. The consultant has prepared<br />

the bid specifications for the exploratory well and the City advertised the project for bidding to select a driller. The bid<br />

opening occurred on January 9, 2008. Hausinger and Associates Inc. was the lowest bidder. The City approved the<br />

contract with Hausinger and Associates Inc. on February 18, 2008. Construction started March 5, 2008 on the<br />

exploratory well. The pilot hole was drilled to <strong>10</strong>40 feet in depth. It was determined by the consultant that the lower zone,<br />

a non USDW zone, is not suitable for ASR development. The decision was made to perform all water quality and<br />

geological tests and back plug this well to a depth of about 520 feet bls. This well was completed and will be the Storage<br />

Zone Monitor Well (SZMW) for this ASR. The ASR will need to be constructed in the Swuannee Limestone aquifer which<br />

is between 400 and 520 feet bls. A technical memorandum on the exploratory/SZMW was completed and submitted to<br />

FDEP in December 2008. The project has been placed on hold pending the results of the District's arsenic pretreatment<br />

study at the City of Bradenton ASR project which has been delayed due to the drought and is now scheduled to be<br />

available in January 20<strong>10</strong>. To date, the District has reimbursed the City $223,809 for it's share of design and construction<br />

of the exploratory/SZMW.<br />

0<strong>21</strong> - Manasota Basin 291