H080<br />

Polk Central Florida Water Resource Development Project<br />

Status As Of: September 08, 2009<br />

The Polk County Comprehensive Water Supply Plan (PCCWSP) (H072) was completed in July 2009. A preliminary list of<br />

projects from the Water Supply Plan was available in December 2008 to aid in the selection of an alternative water<br />

supply project. On December 17, 2008 the Polk County Board of County Commissioners (BOCC) approved the<br />

agreement with the District designating approximately $2.5 million in West Central Florida Restoration Action Plan<br />

(WRAP) funds to Alternative Water Supply (AWS) projects listed on the PCCWSP (H072) - short list. On August 5, 2009<br />

the Polk County BOCC approved the PCCWSP. In a letter dated May 14, 2009 Polk County prioritized projects to receive<br />

WRAP funds and decided to fund the following three projects: (1) Polk County NERUSA Holly Hill Reclaimed Water<br />

Storage and Pumping and Lower Floridan Aquifer Well (H090); (2) Polk County SWRUSA Reclaimed Water Connection<br />

to TECO (H091); and (3) Polk County NWRUSA Reclaimed Water Storage and Pumping Station (N024). As mentioned<br />

above in the Cost Section of this report, WRAP and District appropriations will be transferred to the projects selected by<br />

Polk County (H090, H091 and N024) and resulting in the closing of this project number (H080).<br />