N075<br />

City of Winter Haven Northern Reuse Service Area Reclaimed Main<br />

Extension<br />

Critical Project Milestones Projected Amended Actual<br />

Execute Agreement 11/30/08 2/24/09<br />

Begin Design 1/1/09 2/24/09<br />

Complete Design 6/1/09 6/2/09<br />

Begin Construction 9/1/09<br />

Complete Construction 4/1/<strong>10</strong><br />

Contract Closeout 4/1/11<br />

Offset Report 4/1/12<br />

Status As Of: August 19, 2009<br />

A Cooperative Funding Agreement was executed on February 24, 2009 and David C. Carter Consulting Engineering,<br />

LLC has completed design June 2, 2009. The city submitted design plans and bid documents for District approval in<br />

August. While the documents generally appeared to reflect the agreed-upon project and were approved, the city will need<br />

to ensure that another customer is identified. The original Project #6 in Exhibit B for 2,850 linear feet of 12" reclaimed<br />

water line along Havendale Boulevard to connect Spring Lake, serving a potential 186 residential units, was omitted from<br />

the design plans due to development funding. The Peace River Basin Board approved the transfer of $120,328 in Water<br />

Protection and Sustainability Trust Funds from the cancelled L485 cooperative funding project on October 3, 2008 and a<br />

budget transfer has been completed. To date, $320,328 has been encumbered and $225,000 has been budgeted, of<br />

which $0 has been reimbursed. Governor Crist's Accelerate Florida Initiative ACTION-TO-DATE: On-time. The<br />

cooperator has indicated that the anticipated construction date is still scheduled for the beginning of September 2009.<br />

District staff will coordinate with the cooperator monthly to ensure that a contractor is selected and given notice to<br />

proceed with construction in a timely manner.<br />

020 - Peace River Basin 335