B206<br />

Maintenance of Watershed Parameters & Models<br />

Project Type Basin Initiatives<br />

AOR(s)<br />

Flood Protection, Water Quality, Natural Systems<br />

Basin(s) General Fund (District), Alafia River, Hillsborough River, Northwest Hillsborough, Coastal Rivers,<br />

Pinellas-Anclote River, Withlacoochee River, Peace River, Manasota<br />

Cooperator(s)<br />

Project Manager MCCLUNG, GORDON<br />

Task Manager(s)<br />

Status Ongoing<br />

Citrus County, Hernando County, Pasco County, Polk County<br />

ALTMAN, GENE, LETASI, SCOTT, TURNER, DAWN, MAYER, RICHARD, WALKER, LARRY<br />

Description<br />

This was a basin initiative to fund the Maintenance of Watershed Parameters and Models element of the District's<br />

Watershed Management Program (WMP) for FY2006 to FY2009. For FY20<strong>10</strong> the unit code is being changed from<br />

B206 to a B300 series, 300 general, and B301 to B316 to better account for the maintenance by county.<br />

Benefits<br />

A WMP provides a method to evaluate the capacity of a watershed to protect, enhance, and restore water quality and<br />

natural systems, while achieving flood protection. The information developed assists local governments with their land<br />

management responsibilities by establishing a level of service and developing Best Management Practices (BMPs) to<br />

address level of service deficiencies. In addition, the information provides the District with the best available<br />

information to evaluate adverse impacts and mitigation of floodplain impacts for proposed ERPs. The continuous<br />

maintenance of watershed parameters in the GIS database as ERP permits are approved and new information is<br />

provided to the District through either aerial topographic mapping and its public review and comment period will<br />

provide the most up to date information about the watershed. If a watershed model has not been developed, the<br />

maintenance of parameters in the GIS processes the information in a format that will save time and funding when the<br />

watershed is modeled.<br />

Costs<br />

In FY2005, the Governing Board contributed $80,000 and each Basin Board contributed an additional $<strong>10</strong>,000 each to<br />

support the development of the District's maintenance process. The maintenance budget for FY2006 is $848,000, of<br />

which the District's share is $808,000. Hernando and Polk Counties contributed $20,000 each in FY2006 for<br />

maintenance within their jurisdiction. The maintenance budget for FY2007 is $1,094,200, the District's share is<br />

$924,200. Hernando County ($25,000), Pasco County ($125,000) and Polk County ($20,000) are contributing the<br />

indicated funding in FY2007 for maintenance. An additional $75,000 in FY2007 funds budgeted by the Coastal Rivers<br />

Basin Board for Spring Hill Lakes Management Plan (L775) has been transferred to this project after the Basin Board<br />

approved Hernando County's request to use these funds to perform maintenance based on percolation information<br />

collected from ERPs and Hernando County. The maintenance budget for FY2008 was $2.167 million, of which the<br />

District's share is approximately $1.597 million. For FY2009 Citrus, Hernando, Marion, and Pasco counties are<br />

contributing funds. For FY2009, funding distribution is as follows: Governing Board $1,797,250 (includes Green<br />

Swamp $57,284) Alafia River $78,203; Hillsborough River $366,486; Northwest Hillsborough $13,050; Coastal Rivers<br />

$431,638; Pinellas-Anclote $86,<strong>21</strong>1; Withlacoochee River $181,495; Peace River $182,333; Manasota $154,450. The<br />

following revenue will be received: Citrus County $90,000; Marion County $31,000; Pasco County $500,000; Polk<br />

County $20,000. The revenue will be distributed as follows: Green Swamp $3,684; Alafia River $3,553; Hillsborough<br />

River $<strong>21</strong>5,980; Coastal Rivers $271,460; Pinellas-Anclote $40,950; Withlacoochee River $92,940; Peace River<br />

$12,433.The budget is based on the projected number of approved ERP permits and the average development area<br />

within each Basin. Local government funds are equally matched by Governing Board and Basin Board funds. The<br />

Governing Board is also providing funds specifically to address public meetings and unforeseen issues with projecting<br />

the floodplains to be used in the FEMA mapping process.<br />

Additional Information<br />

A WMP includes five major elements: 1) Topographic Information, 2) Watershed Evaluation, 3) Watershed<br />

Management Plan, 4) Implementation of Best Management Practices, and 5) Maintenance of Watershed Parameters<br />

and Models. Implementing elements of the WMP with local governments is one of the Comprehensive Watershed<br />

Management (CWM) initiative strategies and one of the District's Strategic Priorities. After the Topographic<br />

Information, Watershed Evaluation and Management Plan elements are completed, the watershed parameters and<br />

models require continuous maintenance to simulate the watershed's characteristics as the land form changes. The<br />

watershed's parameters change with the rapid growth being experienced in the District. If continued maintenance of<br />

the models is not performed, the watershed parameters and model will no longer represent the system. This limits<br />

their value in the areas of ERP and flood protection programs. For FY2005, the District managed this project by<br />

issuing work orders for the tasks needed to develop the maintenance process, and then by monitoring the efforts.<br />

FY2006 funds will be used to begin implementing the maintenance process throughout the District in watersheds with<br />

ongoing or completed Watershed Management Plans. For FY2007 this effort will be continued District wide for all<br />

020 - Peace River Basin 93