F032<br />

Peace River Regional Reservoir Expansion<br />

District Budgeted - Ad Valorem Based<br />

Revenue<br />

0<strong>10</strong> General Fund (Districtwide) 8,474,060 1,852,024 4,234,813 5,573<br />

0 14,566,470<br />

020 Peace River Basin 2,3<strong>21</strong>,456 500,046 500,000 600,777<br />

0 3,922,279<br />

0<strong>21</strong> Manasota Basin 6,123,474 1,351,983 3,085,656 43,917<br />

0 <strong>10</strong>,605,030<br />

District Budgeted - Outside Revenue<br />

Water Protection & Sust T.F.<br />

(Alternative Wtr)<br />

Prior<br />

Funding<br />

Cumulative FY 2009 FY20<strong>10</strong><br />

Transfers Funding Funding<br />

8,112,643 1,464,277 0<br />

0<br />

0<br />

9,576,920<br />

Project Funds Not Budgeted by the<br />

District<br />

PR/MRWSA 38,418,817 0 0<br />

0<br />

0 38,418,817<br />

Total:<br />

Future<br />

Funding<br />

Total<br />

Funding<br />

$77,089,516<br />

Critical Project Milestones Projected Amended Actual<br />

Design Commence 2/1/03 2/5/03<br />

Draft Agreement returned from Contract Administration 5/1/03 6/6/07<br />

Peace River Basin Board Approval of Agreement 6/2/03 6/13/03<br />

Manasota Basin Board Approval of Agreement 6/2/03 6/18/03<br />

Governing Board Approval of Agreement 6/2/03 6/24/03<br />

Contract Executed 8/1/03 12/18/03<br />

Notice to Proceed 8/1/03 12/18/03<br />

Basis of Design Report 9/30/05 11/9/05<br />

Execute Amended Agreement 12/31/05 3/28/06<br />

Detailed Plans and Specifications 9/30/06 9/30/06<br />

Permitting 9/30/06 5/7/07<br />

Bidding 11/15/06 6/8/07<br />

Award Construction Contract 11/30/06 7/25/07<br />

50% Construction Completion 11/30/07 8/31/08<br />

Completion of Construction <strong>10</strong>/31/08 3/31/<strong>10</strong><br />

Contract Termination <strong>10</strong>/1/16<br />

Status As Of: September <strong>10</strong>, 2009<br />

Final design for the Regional Reservoir Expansion was completed in 2007 and the Environmental Resource Permit<br />

(ERP)s for mitigation and reservoirs were issued respectively by April 2007 and October 2007. In June 2007, the<br />

Authority received three bids for the reservoir expansion. The low bid of $64,9<strong>10</strong>,500 was <strong>21</strong> percent higher than the<br />

engineer's estimate. The Authority asked the District to provide additional funding for the increased costs and as a result<br />

the Peace River and Manasota Basin Boards and the Governing Board approved an additional $3,703,704 in 2008<br />

funding and $7,812,582 in 2009 funding for the reservoir project. The Governing Board granted various easements to<br />

PRMRWSA in November after receiving survey information and draft easements. The Authority Board approved the<br />

reservoir construction contract at its July 25, 2007 meeting and issued a limited notice to proceed to the Contractor to<br />

begin initial work and permitting. In addition, the Army Corps of Engineers issued the companion permit to the ERP on<br />

May 18, 2007. The District agreed to convey a perpetual exclusive easement and a perpetual nonexclusive easement to<br />

the Authority by September 2007. The District will also convey a conservation easement to the DEP over the mitigation<br />

area to satisfy permit requirements established by DEP. District and Authority staff agreed on public use issues<br />

associated with the Reservoir Expansion project. DEP approved the commencement of construction in December 2007.<br />

In preparation for the construction, District and Authority staff relocated all recreational amenities to accommodate the<br />

project. The dedication ceremony was held on May 15, 2009, with FDEP Secretary Mike Sole and SWFWMD Executive<br />

Director Dave Moore in attendance. Installation of the soil cement and the outlet tower were complete by May 2009. The<br />

project reached the substantial completion milestone on June 25, 2009; five days ahead of the updated schedule. In<br />

total, approximately 3.6 million yards of fill have been moved to build the reservoir's embankment.<br />

0<strong>21</strong> - Manasota Basin 194