10.12.2012 Views

MANASOTA & PEACE RIVER BBDs Meeting Notebook 10-21-09.docx

MANASOTA & PEACE RIVER BBDs Meeting Notebook 10-21-09.docx

MANASOTA & PEACE RIVER BBDs Meeting Notebook 10-21-09.docx

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

K120<br />

North Port - Water ASR - Phase V<br />

Project Type Cooperative Funding<br />

AOR(s)<br />

Water Supply<br />

Basin(s) Manasota<br />

Cooperator(s)<br />

Project Manager KELLEY, MIKE<br />

Task Manager(s)<br />

Status Ongoing<br />

City of North Port, City of North Port - Public Utilities<br />

Description<br />

This project consists of an Aquifer Storage and Recovery (ASR) Program in the City of North Port to create an<br />

alternative water supply by treating excess wet season flows from Myakkahatchee Creek and storing it in the<br />

mineralized Floridan aquifer. The location is downtown North Port at the water treatment plant. The goal of the project<br />

is to develop a 1.5 million gallon per day dry season supply. FY2008 funding is for Phase V of the project which is for<br />

the installation and testing of a degasification system and for the injection and recovery of treated water, cycle test 4.<br />

Longer duration cycle tests will follow. These cycle tests should determine the effectiveness of removing dissolved<br />

oxygen from injected water on arsenic mobilization in the aquifer and recovered water. Phase V will finish this project.<br />

Benefits<br />

The goal of this ASR project is to develop a 1.5 million gallons per day (mgd) dry season supply (equivalent to an<br />

annual average of 4<strong>10</strong>,000 mgd). ASR is an effective method of optimizing the supply of water available from the<br />

Myakkahatchee Creek. Combined with the City's allocation from the Peace River/Manasota Regional Water Supply<br />

Authority (PR/MRWSA), this ASR project has the potential to enable the City of North Port to meet its needs until<br />

approximately 2014.<br />

Costs<br />

The FY20<strong>10</strong> funding request for $60,000 is to continue FDEP required sampling and testing of water quality in the<br />

monitor wells through 2009 and 20<strong>10</strong> while this project is on stand by. This project will continue when we have<br />

favorable, recovery water quality results from the cycle testing at the Bradenton ASR site. The estimated total cost to<br />

conduct Phase V of the project is $619,000 and will be shared by the Manasota Basin Board and the City of North Port<br />

on a 50/50 cost-share basis ($309,500 each). The Basin's contribution will be provided as follows: $75,000 previously<br />

approved in the Basin's FY2007 budget; $126,000 that is in the FY2008 budget; and the remaining $<strong>10</strong>8,500 is in the<br />

FY2009 and future budget years. Funding for FY2009 is combined with approved funding for FY2008 to expand Phase<br />

V of the project to monitor and finish cycle test 4, and run additional longer cycle tests at the City's ASR site. The total<br />

cost of the project is approximately $2,000,000 including prior phases I-IV and funding through FY20<strong>10</strong>. The Manasota<br />

Basin Board and the City of North Port each contributed about $1,000,000.<br />

Additional Information<br />

Phase I determined ASR was the most effective method of optimizing the supply of water available from North Port<br />

Utility's only local source, the Myakkahatchee Creek. The objective of Phase I was to determine the feasibility of ASR<br />

at the North Port water treatment facility, and compare its merits and disadvantages with those of other forms of water<br />

storage, primarily aboveground facilities. During Phase II, the City's consultant designed the ASR well system and<br />

acquired construction and water use permits from the FDEP and the District. They also applied for a Class V injection<br />

well permit from the FDEP. Phase III included construction and testing of the ASR well and monitor wells, and project<br />

report writing. Phase III was initiated July 2001 and is complete. Line item adjustments have been made to Phase III to<br />

change the focus of this ASR project from treated raw water to fully treated potable water ASR. Cycle tests one and<br />

two were included in Phase III. Phase IV of the City's pilot ASR Program includes engineering services, hydrogeologic<br />

field work, data collection and analysis, laboratory analytical services and completion report to accommodate the third<br />

cycle test as required by the FDEP UIC permit for the project. The third cycle test was not included, as it was not<br />

anticipated to be required by the FDEP at the time the Phase III agreement was finalized. The Phase III agreement is<br />

being extended to 12/31/2005 to allow sufficient time to complete all activities related to finalization of the second cycle<br />

test. Completion of the cycle test was hampered for a couple of reasons. First, the start of the injection portion of the<br />

test was delayed due to a lack of water when the city was providing emergency water supplies to the PR/MRWSA<br />

after Hurricane Charley hit the area in August 2004. The second major reason was the fact that the recovery portion of<br />

the test was halted prematurely when the recovered water, which was directly discharged into Myakkahatchee Creek,<br />

exceeded the standard for arsenic concentration of 50 micrograms/liter (ug/L). The DEP was contacted and the<br />

second cycle test is considered complete. A third cycle test began 8/2/2005 and injected a million gallons per day of<br />

treated water for 75 days which was to remain in storage 30 days. Recovery is delayed due to the construction of a lift<br />

station to pump recovered water to the wastewater treatment plant because initial recovered water is anticipated to<br />

exceed the 50 ug/L arsenic limit. When recovered water quality is below 50 ug/L arsenic the discharge will be to<br />

Myakkahatchee Creek. The recovered water during Cycle Test 3 was all discharged into the sanitary sewer system.<br />

0<strong>21</strong> - Manasota Basin 244

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!