B263<br />

Evaluation of Different On-Farm Blueberry Systems To Improve<br />

Irrigation Efficiency<br />

Prior Cumulative FY 2009 FY20<strong>10</strong><br />

Funding Transfers Funding Funding<br />

District Budgeted - Ad Valorem Based<br />

Revenue<br />

0 0 0 23,300<br />

0<strong>10</strong> General Fund (Districtwide) 0 23,300<br />

011 Alafia River Basin 0 0 3,406<br />

0<br />

0 3,406<br />

013 Hillsborough River Basin 0 0 2,<strong>21</strong>2<br />

0<br />

0 2,<strong>21</strong>2<br />

015 Coastal Rivers Basin 0 0 3,<strong>10</strong>5<br />

0<br />

0 3,<strong>10</strong>5<br />

019 Withlacoochee River Basin 0 0 5,497<br />

0<br />

0 5,497<br />

020 Peace River Basin 0 0 9,080<br />

0<br />

0 9,080<br />

Total:<br />

Future<br />

Funding<br />

Total<br />

Funding<br />

$46,600<br />

Critical Project Milestones Projected Amended Actual<br />

Develop Contract 11/3/08 <strong>10</strong>/3/08<br />

Notice To Proceed 2/2/09 2/18/09<br />

Mailed Contract to University 12/1/09 12/1/08<br />

Year 1 Data Collection 12/31/09<br />

Year 2 Data Collection 12/31/<strong>10</strong><br />

Final Report 6/30/11<br />

End of Agreement 1/31/12<br />

Status As Of: June <strong>10</strong>, 2009<br />

2/18/2009 - Sent Notice to proceed. 3/6/2009 - Ordering material. 4/20/2009 - Mobilizing equipment 6/<strong>10</strong>/2009 - Waiting<br />

for equipment to arrive 9/1/2009 - data collection, project continuing as planned.<br />

020 - Peace River Basin 132