B206<br />

Maintenance of Watershed Parameters & Models<br />

Ten (<strong>10</strong>) Consultant Agreements Execution 9/30/06 11/15/06<br />

First Amendment to Management Services 4/16/07 4/18/07<br />

First Amendment Execution 6/19/07 7/30/07<br />

Contract Termination <strong>10</strong>/31/08 5/31/11<br />

4. FY2007 Consultant Services Agreements<br />

Draft Agreements to Management Services 3/12/07 4/17/07<br />

Draft Agreements returned from Management Services 5/22/07 5/15/07<br />

Consultant Agreements Execution 6/19/07 8/1/07<br />

Notice to Proceed to Consultants 7/1/07 8/<strong>10</strong>/07<br />

Contract Termination 5/31/11<br />

5. Hernando County Maintenance<br />

Draft Agreement to Management Services 3/31/05 3/25/05<br />

Draft Agreement returned from Management Services 4/15/05 4/20/05<br />

Contract sent to County for signature 8/20/06 11/9/06<br />

County Contract Execution 12/<strong>10</strong>/06 12/12/07<br />

County Contract Expiration <strong>10</strong>/31/<strong>10</strong><br />

6. Polk County Maintenance<br />

Draft Agreement to Management Services 8/9/05 8/9/05<br />

Draft Agreement returned from Management Services 8/23/05 8/23/05<br />

Contract sent to County for signature 8/25/05 8/25/05<br />

Contract Execution <strong>10</strong>/31/05 12/2/05<br />

Draft First Amendment to Management Services 7/24/07<br />

Draft First Amendment returned from Management Services 8/24/07<br />

First Amendment sent to County for signature 9/4/07<br />

First Amendment Execution <strong>10</strong>/1/07<br />

Contract Termination 6/30/09<br />

7. Pasco County Maintenance<br />

Draft Agreement to Management Services 4/3/07 4/3/07<br />

Draft Agreement returned from Management Services 4/23/07 4/23/07<br />

Contract sent to County for signature 5/4/07 5/4/07<br />

Contract Execution 7/28/07 7/28/07<br />

Contract Termination 12/31/09<br />

Status As Of: July 15, 2008<br />

FY2005: The consultant services agreement with URS Corporation Southern was executed on June 6, 2005. Notice to<br />

proceed was issued on the same date. Work Order #1 has been developed to investigate the current data (type, quality,<br />

quantity, etc.) entering the District through ERP and to develop a proposed work flow to maintain the watershed<br />

parameters and models as permits are approved. A kick-off meeting with the consultant team and District staff was held<br />

on June 14th to introduce and plan the project with all departments that will be involved, including: Technical Services,<br />

Legal, and Resource Management. The final report has been accepted. Remaining funds are being used to develop<br />

presentation and documentation of an example project to be distributed to cooperators, FEMA, and other District WMP<br />

consultants who will be performing maintenance beginning with FY2006 funds. Work Order #2 has been executed to<br />

document the maintenance process step-by-step. The consultant has completed the example maintenance project along<br />

with accompanying documentation and presentation. This contract has been terminated and the final payment<br />

processed. FY2006 : Staff has developed consultant services agreements with ten (<strong>10</strong>) WMP consultants to begin<br />

maintenance of watershed parameters and models. Maintenance efforts will first be directed at completed and ongoing<br />

Watershed Management Plans. The District's consultants who originally prepared the Watershed Management Plans will<br />

be typically tasked with maintenance of their respective watershed(s). Work orders will be issued as project(s) with<br />

approved ERP(s) are identified or new site conditions data become available. Basin Board funding will only be used for<br />

maintenance activities within the Basin. Consulting services agreements were executed by November 15, 2006, with all<br />

<strong>10</strong> consultants including: Ardaman; Ayres & Associates; BCI; Dyer Riddle Mills & Precourt; Jones Edmunds; Keith<br />

Parsons; Post Buckley Schuh & Jernigan; TBE Group; and URS. Amendments have been executed for these <strong>10</strong><br />

agreements to increase the total compensation for approved FY2007 and anticipated FY2008-2011 funding, extend the<br />

contract termination date, and revise the scope of work to be consistent with current WMP agreement language.<br />

FY2007: An additional nine (9) agreements have been executed with the remaining consultants approved to perform<br />

elements of the District's WMP. All 19 consultant services agreements will support District-wide maintenance. Each<br />

consultant has been assigned specific watersheds for maintenance. Project managers within the Engineering Sections<br />

will be responsible for developing and executing work orders with each of these consultants. Guidelines and<br />

020 - Peace River Basin 95