(Completed) Lake Eva Water Quality Improvement Project<br />

Prior<br />

Funding<br />

Cumulative FY 2009 FY20<strong>10</strong><br />

Transfers Funding Funding<br />

District Budgeted - Ad Valorem Based<br />

Revenue<br />

020 Peace River Basin 0 0 252,846 1,977<br />

0 254,823<br />

Project Funds Not Budgeted by the<br />

District<br />

City of Haines City 250,000 0 0<br />

0<br />

0 250,000<br />

Total:<br />

Future<br />

Funding<br />

Total<br />

Funding<br />

$504,823<br />

Critical Project Milestones Projected Amended Actual<br />

1. Contract Development & Execution<br />

Agreement Sent to Contracts Administration <strong>10</strong>/5/08 2/2/09<br />

Agreement Approved by City Council 11/5/08 5/<strong>21</strong>/09<br />

Contract Executed 12/30/08 6/12/09<br />

Notice to Proceed 12/30/08 6/12/09<br />

3. Preliminary Design<br />

Preliminary Design 2/28/09 11/7/08<br />

4. Final Design and Permitting<br />

60 and 90 Percent Plans 6/30/09 2/18/09<br />

Permitting 8/30/09 5/8/09<br />

5. Construction<br />

Construction Bidding 11/30/09<br />

Construction Services 6/30/<strong>10</strong><br />

Status As Of: August 28, 2009<br />

The preliminary design plans for this project were revised by the City to modify the outfall location of the stormwater<br />

retrofit. A second permitting pre-application meeting was held on August <strong>21</strong>, 2008 to review the modifications to the<br />

project preliminary design plans and review permit requirements. District staff provided a template of a scope of work to<br />

the City's consultant in September 2008 and a project scope of work was completed by the City and District by the end of<br />

January 2009. The final contract and scope of work was drafted by District staff and submitted for internal review and<br />

approval during the second week of February 2009. The agreement was approved by the City on May <strong>21</strong>, 2009 and the<br />

fully executed by the District on June 12, 2009. The City's Contractor has initiated work on the project and has completed<br />

approximately 50 percent of the project construction. Construction has been completed by the middle of August 2009.<br />

Final invoicing is underway. The project was completed ahead of schedule and below budget.<br />

020 - Peace River Basin 331