L200<br />

Bradenton - Wares Creek Bridge Replacement<br />

4C. Fourth Amendment (FY2009 Funding)<br />

Amendment Executed 1/31/09 3/27/09<br />

FY2009 Funds Encumbered 2/1/09 11/7/08<br />

4D. Consultant & Construction Services (FY2009 Funding)<br />

Plans & Profiles for 4bridges sufficient to submit for permits 12/31/08<br />

Bidding & Contr. Selection for 12th Ave. Bridge 11/30/<strong>10</strong><br />

Contract Award for 12th Ave. Bridge 3/1/11<br />

Commence Construction of 12th Ave. Bridge 5/1/11<br />

5. Contract Completion<br />

Cooperator Agreement Expiration <strong>10</strong>/1/07 12/31/11<br />

Status As Of: August 24, 2009<br />

Status History: The Cooperative Funding Agreement was executed on December 29, 2004. The City contracted with<br />

Jones Edmunds & Associates (JEA) to perform the engineering work on the project. Topographic surveying and<br />

geo-technical work were completed and existing hydraulic & hydrologic data were collected. The City requested<br />

additional cooperative funding for FY2006 and a contract amendment to incorporate the FY2006 funds was executed on<br />

September <strong>21</strong>, 2006. A preliminary hydrologic and hydraulic report was submitted. The City applied for FY2007 funding<br />

to perform additional field survey work, to perform additional hydraulic and hydrologic studies and to begin construction of<br />

the 9th Avenue Bridge. The Preliminary Design Report was submitted on June 12, 2006 and comments were provided to<br />

the City. The hydraulic modeling of Wares Creek was submitted for review and comments on October 20, 2006. District<br />

staff met with the City's consultant in March 2007 to discuss the results of the hydraulic modeling. A pre-application<br />

meeting with Sarasota Regulatory staff was held on April 25, 2007 to discuss the project. City staff is concerned with the<br />

status of the water quality certificate (WQC) which the Army Corps of Engineers (ACOE) is requesting from the FDEP, in<br />

particular, with the conditions which might be attached to the WQC and what additional work may be required in order for<br />

the City to obtain a permit from the District. The consultant is continuing work on the modeling of the creek hydraulics<br />

and hydrology. A progress meeting was held at District headquarters on April 28, 2008 to discuss the modeling effort,<br />

future cooperative funding, ACOE permitting status and other items. The City's consultant (JEA) met with the Sarasota<br />

Regulatory staff on August 20, 2008 for a second pre-application meeting. District staff met with the city project manager<br />

and the consultant on October 16, 2008 to discuss project status and progress. Action-to-date: This project has been<br />

delayed partly in response to the delays in the ACOE proceeding with the Wares Creek Dredging project. The City is<br />

working with FDOT to see if Federal stimulus funding is available for this project. The City's consultant is continuing with<br />

data gathering and modeling in preparation for submitting a permit application for the 9th Avenue Bridge. The fourth<br />

amendment to the cooperative funding agreement was executed. This amendment adds the FY2009 cooperative funding<br />

and revises the project schedule.<br />

0<strong>21</strong> - Manasota Basin 267