L614<br />

Sarasota Imp. BMPs Matheny Creek<br />

Critical Project Milestones Projected Amended Actual<br />

1. Contract Development & Execution<br />

Negotiate Cooperative Funding Agreement with County <strong>10</strong>/31/06 1/5/07<br />

Draft Agreement to Management Services 1/5/07 2/15/07 2/2/07<br />

Agreement returned from Management Services 3/14/07 3/14/07<br />

Contract sent to County for BOCC Approval 3/14/07 3/14/07<br />

Signed Contract returned from County 4/2/07 4/30/07<br />

Contract Execution 4/16/07 5/3/07<br />

Notice to Proceed 4/16/07 5/3/07<br />

2. Critical Project Milestones<br />

Complete Design and Permitting 6/5/07 4/1/09 4/1/09<br />

Bidding and Contractor Selection 11/5/07 <strong>10</strong>/30/09<br />

Commence Construction 11/5/07 12/31/09<br />

Complete Construction 1/5/09 9/1/<strong>10</strong><br />

3. Project Close Out<br />

Submit As-Builts 5/5/09 11/1/<strong>10</strong><br />

Contract Termination 11/30/<strong>10</strong><br />

Status As Of: August 26, 2009<br />

Notice of FY2007 funding approval was sent to the County's project manager. A meeting was held with the County in<br />

August 2006 to discuss the scope of work and schedule. The County submitted a FY2008 funding request in the amount<br />

of $<strong>21</strong>2,500 to cover second year funding of the multi-year funded project. Notice to Proceed was sent to the cooperator<br />

effective May 3, 2007. The Manasota Basin Board included the second year funding request of $<strong>21</strong>2,500 in its FY2008<br />

budget. The ERP modification for the baffle box is completed. The FDOT utility drainage permit and temporary<br />

construction easements were acquired. The County is updating the construction plans to accommodate utility<br />

adjustments along US 41. District staff met with the County on December 29, 2008 to discuss the project status. Design<br />

and Permitting were completed in April 2009. The construction component of the project was advertised for bid on<br />

August 22, 2009. The contractor pre-bid meeting is scheduled for September 3, 2009.<br />

0<strong>21</strong> - Manasota Basin 299